Routing the cables
This procedure describes connecting cables and use of the two hook and loop straps
provided in the rail kit to route the cables at the back of the server.
Procedure
1. Connect I/O and power cables as described in your system cabling
documentation.
2. Locate the outer CMA brackets on the interior sides of both cabinet flanges (1).
3. Bundle the cables gently, pulling them clear of the server connectors to the left
and right sides (2).
4. Thread the hook and loop straps through the tooled slots on the outer CMA
brackets on each side of the server to secure the cable bundles (3).
Figure 31 Hook and loop straps
Install bezel
Bezels are application specific, and may not appear as shown. This procedure can be
used to install all bezels.
Procedure
1. Position right side of bezel on the server bracket. Rotate the bezel inward so
that it is flush with front of the server and the latch on the left side secures the
bezel.
2. Lock the bezel with the provided key and store the key in a secure place.
2U1N Configuration Equipment Installation
68
Hardware Installation Guide
Summary of Contents for EMC VxFlex Ready Node 13G
Page 1: ...Dell EMC VxFlex Ready Node 13G Hardware Installation Guide 302 002 955 REV 05 ...
Page 6: ...FIGURES 6 Hardware Installation Guide ...
Page 8: ...TABLES 8 Hardware Installation Guide ...
Page 16: ...1U1N Procedures 16 Hardware Installation Guide ...
Page 58: ...2U1N Procedures 58 Hardware Installation Guide ...
Page 69: ...Figure 32 Install the bezel 2U1N Configuration Equipment Installation Install bezel 69 ...
Page 70: ...2U1N Configuration Equipment Installation 70 Hardware Installation Guide ...