Table 18 Management network cabling (continued)
Customer Provided Management Switch
Source
Destination
Node 17 BMC (iDRAC)
Management Switch Port 29
Node 17 NIC 1
Management Switch Port 31
Data Network Switch A <...> Port
Management Switch Port 45
Data Network Switch B <...> Port
Management Switch Port 46
Data Network Switch A Mgmt Port
Management Switch Port 47
Data Network Switch B Mgmt Port
Management Switch Port 48
Management Server NIC 1
Management Switch Port 38
Link to Core Switch or 2nd Rack Management
Switch
Management Switch Port 52
Data network A wiring for 2U1N configuration
Use the following figure and table to connect the data network A cables.
Note
In this example, data switch ports have been intentionally left empty. These empty
ports can be used for other user-allocated purposes. If no other use is required for the
empty ports, nodes may be connected to the data switches without leaving empty
ports. However, ensure that on each node, each NIC is connected to a different data
switch (either Data Switch A or Data Switch B), in order to prevent a single point of
failure in case a switch fails.
Wiring Diagrams for a 2U1N Configuration
82
Hardware Installation Guide
Summary of Contents for EMC ScaleIO Ready Node 14G
Page 1: ...EMC ScaleIO Ready Node 14G Hardware Installation Guide 302 004 321 REV 01 ...
Page 6: ...FIGURES 6 Hardware Installation Guide ...
Page 8: ...TABLES 8 Hardware Installation Guide ...
Page 16: ...Before You Begin 16 Hardware Installation Guide ...
Page 18: ...1U1N Procedures 18 Hardware Installation Guide ...
Page 40: ...1U1N Configuration Equipment Installation 40 Hardware Installation Guide ...
Page 48: ...Install AC Power Cables 48 Hardware Installation Guide ...
Page 62: ...2U1N Procedures 62 Hardware Installation Guide ...
Page 74: ...2U1N Configuration Equipment Installation 74 Hardware Installation Guide ...