Installing an intrusion switch
Prerequisites
Follow the safety guidelines listed in
Steps
1
Slide the intrusion switch into the intrusion switch slot.
2
Route the cables through the cable routing hooks on the side of the system.
3
Lower the cable management bracket into the system.
4
Press the bracket and insert the tabs on the bracket into the slots on the right side of the system.
5
Connect the cable to the connector (INTRUSION) on the system board.
Figure 32. Installing an intrusion switch
Next steps
1
Lift the sides of the fan tray until the blue release tabs click in place.
2
If applicable, install the PEM.
3
If applicable, install the expansion card risers.
4
Install the air shroud.
5
Install the fan cage.
6
Follow the procedure listed in
After working inside your system
.
Installing and removing system components
79