Functions
PICUS
• Free-of-charge PC software
• Set up permissions
• Configure controller inputs, outputs, and parameters
• See live data
• Controller software updates
Documentation
◦ Data sheet
◦ Quick start guide
◦ Designer's handbook
◦ Installation instructions
◦ Commissioning guidelines
◦ Operator's manual
◦ PICUS manual
◦ Modbus table
• Context-sensitive help in the display unit
4.3.2 Sync. check OK relay
If the
Sync. check OK
relay function is configured, then DEIF recommends that you test it.
DANGER!
You MUST complete all the previous commissioning steps.
To test the function:
1. Connect a synchroscope across the breaker.
2. Connect a light to the
Sync. check OK
relay.
3. The breaker must be open.
4. There must be power on the busbar.
5. Start the genset.
6. Whenever the synchroscope shows that the busbar and generator are synchronised, the
Sync. check OK
light should be
lit.
Troubleshooting
If the
Sync. check OK
light is not lit when the synchroscope shows that the busbar and generator are synchronised:
• Check that the light works.
• Check the synchroscope wiring.
• If a breaker
Close
digital output is configured, check that the
Configure > Parameters > Synchronisation > Settings > Type
> Sync. behaviour
parameter is
Sync. check (signal when in sync.)
.
4.3.3 Breaker trip
When you are ready to close the breaker for the first time, DEIF recommends that you test the breaker trip.
GPU 300 Commissioning guidelines 4189341033 UK
www.deif.com
Page 25 of 36