25
23/06/05 - 300002940-001B
DTG 1300 Eco.NOx/V
2 Cleaning heater body
`
Sweep the heater.
`
Take out the burner drawer from the heater body.
`
Do not block the gas ramp openings.
With the burner out :
Take out the column head fixed by 2 screws and toothed washers
Take out the insulation
Open the sweeping trap by unscrewing the 2 screws
Clean the heater body with the special brush delivered with the
product.
To re-assemble, perform the above actions in reverse order.
3 Maintenance
Maintenance and cleaning of the heater must be carried out at least
once a year by a qualified technician.
We advise you against draining the system unless it is
absolutely necessary (For example : Several months' absence
with the risk of ice in the building).
It is recommended that you take out a maintenance contract with a
qualified installation engineer. In the event that this is not possible,
sign a maintenance contract with an after-sales service company
recommended by your installation engineer or
De Dietrich
.
Sweeping the smoke conduct and the purge tank must be carried out
at least once a year during boiler maintenance.
4 Periodic checks on the domestic hot water tank
Titane anode
No maintenance operations
The panel must be switched on to ensure that the anode is
working
Magnesium anode
The titanium anode can be replaced by a magnesium anode.
The magnesium anodes must be checked at least every 2, years.
After the first check, determine the frequency of future checks on the
basis of anode wear. The anodes can be checked by two methods:
- Inspection:
the anode must be replaced if its diameter is less than 15 mm
(original diameter = 33 mm)
- Function test:
- disconnect the earth wire from the anode
3
8518N016
4
1
2
Stages
Actions
Water level
Regularly check the level of water in the system and top up if required, taking care that cold water is not
added suddenly into the boiler when it is hot.
This operation must be carried out several times per season ; if not, look for the probable leak and
immediately fix it.
Ice
In the event that the heating stops during winter, increasing the risk of ice (holiday home for example), it is
recommended that sufficient anti-freeze is used to stop the heating water from freezing.
As a default, completely empty the installation (check with your installation engineer).
Summary of Contents for Elitec DTG 1304 Eco.NOx/V
Page 1: ...DTG 1300 Eco NOx V Gas fired boilers English 23 06 05 Elitec Technical instructions...
Page 31: ...31 23 06 05 300002940 001B DTG 1300 Eco NOx V Gas line Cladding...
Page 32: ...32 DTG 1300 Eco NOx V 23 06 05 300002940 001B Linking kit...
Page 36: ...36 DTG 1300 Eco NOx V 23 06 05 300002940 001B...
Page 37: ...DTG 1300 Eco NOx V 23 06 05 300002940 001B...
Page 38: ...DTG 1300 Eco NOx V 23 06 05 300002940 001B...