Page 1: ... 1 310 6002 0 CAPITAL CONTROLS Instruction Manual Series 1041B ...

Page 2: ...ion to instruction operating manuals all instructions given on labels or attached tags should be followed Regardless of these efforts it is not possible to eliminate all hazards from the equipment or foresee every possible hazard that may occur It is the responsibility of the installer to ensure that the recommended installation instructions are followed It is the responsibility of the user to ens...

Page 3: ...s 11 4 2 1 Automatic Mode 11 4 2 2 Manual Override Mode 13 4 2 3 Empty Indications 13 4 2 4 Closed Indications 13 4 2 5 Emergency Shutdown Failure Indications 14 5 SERVICE 15 5 1 Automatic Switchover 15 5 2 System Shutdown for Routine Maintenance 15 5 3 Expansion Chamber Rupture Disc Replacement Liquid System Only 16 5 4 PLC Reset Instructions 16 5 5 PLC Fault Blinking Red Light 16 6 TROUBLESHOOTI...

Page 4: ...ms Field configurable Safety Features Safety interlocks latching alarm circuit with manual reset automatic remote shutdown Power Requirements 120 Vac or 240 Vac 50 60 Hz single phase Shipping Weight 45 lbs 20 kgs Enclosure NEMA 4X Switches NEMA 4X industrial grade Mounting Wall 1 3 Automatic Switchover System Components See Figures 1 2 and 3 The Series 1041 Automatic Switchover System consists of ...

Page 5: ...ll valve on the stand by source The automatic switchover design uses the mechanical limit switches to prevent either motorized ball valve from opening before the other motorized ball valve is completely closed Manual override is accomplished by selecting the manual mode using the Auto Manual selector switch then manually opening or closing the desired valve using the Side A or Side B Open Closed s...

Page 6: ...3 4 Manual valve 3 4 Valve with motorized operator Pressure switch with diaphragm protector Range 5 30 psig NOTE Manifolds are required for cylinder or ton container withdrawal Figure 2 Automatic Switchover System Gas Withdrawal PS PS ALARM CONTACTS SIDE A SIDE B OPEN CLOSED REMOTE STATUS CONTACT VALVE A VALVE B VALVE A VALVE B SIDE A SIDE B Auto Open Manual Open Close Close Reset SYSTEM DISPENSIN...

Page 7: ...and pressure switch chlorine or sulfur dioxide 1 Valve with motorized operator Pressure switch with diagragm protector Range 5 30 psig chlorine or sulfur dioxide NOTE Liquid withdrawal manifolds are required Figure 3 Automatic Switchover System Liquid Withdrawal PS PS ALARM CONTACTS SIDE A SIDE B OPEN CLOSED REMOTE STATUS CONTACT VALVE A VALVE B VALVE A VALVE B SIDE A SIDE B PI PSH PSH PI PSH PI L...

Page 8: ...3000 pound A 105 Grade No 1 or 2 forged steel fittings be used for chlorine liquid or gas service For chemicals other than chlorine consult appropriate directory recommendations on pipe and fittings for the chemical being dispensed 2 2 3 All threaded connections for chlorine must be sealed with litharge and glycerin or Teflon tape Litharge and glycerin sealed connections cannot be disassembled aft...

Page 9: ...e Figure 4 3 1 2 Valve A and Valve B Motorized Valves must be calibrated as follows a Check the limit switches for 100 closed contact closure b Enter the CALIBRATE mode by depressing and holding the RESET push button until all indicators illuminate and the EMPTY OPEN indicators go out approximately 10 seconds Calibrate mode is now activated c Cycle Valve A to the full open position by setting Side...

Page 10: ... designed for switching sources of liquid or gas a source of gas rather than liquid is used for leak testing To check for leaks proceed as follows a Open and immediately close the container gas outlet valve introducing just enough gas to pressurize the first section of the piping between the source and its respective closed motorized ball valve NOTE All other valves should be open to evacuate the ...

Page 11: ...e c Initiate automatic switchover by setting the mode switch to AUTO and depress and hold the RESET push button until all the indicators go on Valve A will open as indicated by the side A illuminated OPEN indicator while Valve B remains closed and Side B remains in stand by d When the Side A on line source is depleted the EMPTY light for Side A illuminates and feed transfers automatically to Side ...

Page 12: ...l Side B source is replaced EMPTY and STAND BY lights flash indicating Side B source has been replaced m The operator depresses RESET push button completing Side B source replenishment and putting Side B source in stand by status for subsequent automatic switchover to Side B source when Side A on line source becomes depleted Side Empty Open Closed Stand by A O O O B O O Valve A open and Side A fee...

Page 13: ...s depleted the EMPTY light for Side A will flash 4 2 4 CLOSED Indications Side Empty Open Closed Stand by A O O O B O O Valve A open and Valve B closed Side B in stand by Side Empty Open Closed Stand by A O O O B O O Valve A closing Side B in stand by Side Empty Open Closed Stand by A O O B O O O Valve B open and Valve A closed and Side A in standy by Side Empty Open Closed Stand by A O O B O O Va...

Page 14: ...ont Side Empty Open Closed Stand by A O O B O O Remote shutdown of both valves automatic switchover is connected to external alarm devices such as gas fire or smoke detectors Side Empty Open Closed Stand by A B Valve A failure limit switch open system halted Side Empty Open Closed Stand by A B Valve B failure limit switch open system halted Side Empty Open Closed Stand by A O O O O B O O O O Re po...

Page 15: ...ne valves at the two independent chemical sources while continuing system operation to evacuate the piping system of chemical c Observe the system status lights on the Automatic Switchover The OPEN light of the side which is dispensing chemical will eventually go out and the EMPTY light on that side will illuminate indicating that chemical between the source and the motorized ball valve has been e...

Page 16: ... 4 PLC Reset Instructions Sometimes a reset of the PLC is required please follow these instructions 5 4 1 Confirm that PLC terminal 18 LED is illuminated indicates 24 volt supply is operational If no LED check the 24V fuse 5 4 2 Power down PLC 5 4 3 Install a jumper between terminals 18 19 of the PLC The jumper allows the controller to disregard all inputs and resets the valve timing delay to 15 s...

Page 17: ...ted See Figure 4 a Power supply failure at source b Blown fuse c Programmable controller failure a Check and reset breaker b Replace fuse c Replace programmable controller 4 Programmable controller shows FAULT See Figure 4 a Program error b 24 Vac power supply failure input 18 not energized See Figure 4 a Consult factory for program instructions b Internal fuse blown replace controller 5 Field dev...

Page 18: ...improvements may be made without notice OCT 2017 De Nora Water Technologies 3000 Advance Lane Colmar PA 18915 ph 1 215 997 4000 fax 1 215 997 4062 web www denora com mail info dnwt denora com Registered Trademark 2017 All Rights Reserved ...