HIGH POST
MODEL: HP
STEP 1
Ensure foot is fully threaded in.
Locate the post and ensure it is visually plumb.
Minimum edge distance: 2” (50 mm)
STEP 2
Remove the lock pin and extend the outer tube
until the head contacts the slab above.
Install the lock pin in the closest hole.
STEP 3
Turn the post counterclockwise until it is tight
and until there is no red showing at the visual
“safe” indicator.
1
2a
2b
3
INSTALLATION
HEAD
VISUAL “SAFE”
INDICATOR
INNER TUBE
LOCK PIN
OUTER TUBE
FOOT
Maximum spacing of High Posts not to exceed 9’ (2743 mm)
WEIGHT: 28 lbs / 12.7 kg
HEIGHT: 8’2”–13’6” / 2489–4115 mm
CLOSED HEIGHT: 7’1” / 2159 mm
When all the steps are completed, the High Post is ready for the
Speed Fence or temporary guardrail to be installed
STORAGE PIN HOLE
MIN 2”
(50
mm)