Operating Guide
Termix VVX Compact 28/18 – 7 Series BS-HC
6.4 Extras
6.4.1 Hot water recirculation pump
When hot water recirculation pump is installed together with
the Pre-Payment unit, it is recommended for the pump to take
Switched Live from Terminal 2 in the heating interface wiring box.
This is to ensure that the pump stops circulating when no credit is
available on the Pre-Payment unit.
6.5 Maintenance
The substation requires little monitoring, apart from routine
checks. It is recommended to read the energy meter at regular
intervals, and to write down the meter readings.
Regular inspections of the substation according to this Instruction
are recommended, which should include:
Strainers
Cleaning of strainers.
Meters
Checking of all operating parameters such as meter readings.
Temperatures
Checking of all temperatures, such as DH supply temperature and
DHW temperature.
Connections
Checking all connections for leakages.
Safety valves
The operation of the safety valves should be checked by turning
the valve head in the indicated direction.
Venting
Checking that the system is thoroughly vented.
Inspections should be carried out minimum every two years.
Spare parts can be ordered from Danfoss. Please ensure that any
enquiry includes the substation serial number.
Authorized personnel only
Assembly, start-up and maintenance work must be performed by
qualified and authorized personnel only.
20
DEN-GT
LGB42404
Summary of Contents for Termix VVX Compact 28/18 - 7 BS-HC Series
Page 24: ...Operating Guide Termix VVX Compact 28 18 7 Series BS HC 24 DEN GT LGB42404...
Page 25: ...Operating Guide Termix VVX Compact 28 18 7 Series BS HC LGB42404 DEN GT 25...
Page 26: ...Operating Guide Termix VVX Compact 28 18 7 Series BS HC 26 DEN GT LGB42404...
Page 28: ...Operating Guide Termix VVX Compact 28 18 7 Series BS HC Produced by Gemina Termix A S 04 2018...