Safety and system checks
Before hoisting the array to its operating position recheck the
actual status of the assembly as follows:
メモ: When applicable, the same system and safety checks
also apply to ground stack assemblies.
4.1 Mechanical setup
▪ Check the attachment of the Load adapter(s) to the Flying frame
and ensure all Locking pins are properly inserted and locked.
▪ Check the attachment of the secondary safety device at the
Flying frame (refer to section
▪ Check the attachment of the Flying frame(s) to the cabinets and
ensure all Locking pins are properly inserted and locked.
▪ Check the attachment of all Front links on both sides of the
cabinets and ensure all Locking pins are properly inserted and
locked.
▪ Check the splay angles and the attachment of the Splay/Rear
links on the rear of the cabinets and ensure all Locking pins are
properly inserted and locked.
▪ In "Single pickpoint operation" check the desired total vertical
aiming of the entire array using an inclinometer.
4.2 Wiring
▪ Check the wiring.
If the amplifiers are already wired and powered on, use their
System check functions or Channel mute switches and a test
signal to check the correct operation and routing of all channels
and cabinets.
4 Safety and system checks
d&b V-Series リギングマニュアル 1.11 ja
36