![Daikin Sky Air Alpha Series Installer'S Reference Manual Download Page 64](http://html1.mh-extra.com/html/daikin/sky-air-alpha-series/sky-air-alpha-series_installers-reference-manual_4705613064.webp)
7
|
Installation
Installer reference guide
64
RZAG71~Y1
Sky Air Alpha-series
4P695307-1 – 2022.05
g
b
a
f
e
c
d
a
Gas pipe
b
Gas pipe insulation
c
Interconnection cable
d
Field wiring (if applicable)
e
Liquid pipe
f
Liquid pipe insulation
g
Finishing tape
2
Install the service cover.
7.8.2 To close the outdoor unit
2
1
4
3
1×
PH2
8
mm
7.8.3 To check the insulation resistance of the compressor
NOTICE
If, after installation, refrigerant accumulates in the compressor, the insulation
resistance over the poles can drop, but if it is at least 1 MΩ, then the unit will not
break down.
▪
Use a 500 V mega-tester when measuring insulation.
▪
Do NOT use a mega-tester for low voltage circuits.
1
Measure the insulation resistance over the poles.
If
Then
≥1 MΩ
Insulation resistance is OK. This procedure is
finished.
<1 MΩ
Insulation resistance is not OK. Go to the next step.
2
Turn ON the power and leave it on for 6 hours.
Result:
The compressor will heat up and evaporate any refrigerant in the
compressor.
3
Measure the insulation resistance again.
Summary of Contents for Sky Air Alpha Series
Page 85: ......
Page 86: ......
Page 87: ......
Page 88: ...4P695307 1 2022 05 Copyright 2022 Daikin Verantwortung f r Energie und Umwelt...