3
|
Components
Service manual
101
250D7Y1B
Sky Air Advance-series
ESIE19-13A – 2020.05
a
b
c
a
Fuse F1U
b
Fuse F2U
c
Fuse F3U
Is the problem solved?
Action
Yes
No further actions required.
No
Return to
continue with the next procedure.
3.10 Noise filter PCB
3.10.1 Checking procedures
INFORMATION
It is recommended to perform the checks in the listed order.
To perform a power check of the noise filter PCB
Prerequisite:
Stop the unit operation via the user interface.
Prerequisite:
Turn OFF the respective circuit breaker.
Prerequisite:
Remove the required plate work, see
1
Access the back side of the switch box, see
111].
2
Turn ON the power of the unit.
3
Measure the voltage between the phases L1A‑L2A‑L3A on the noise filter PCB.
Result:
All measurements MUST be 400 V AC ± 10%.
4
Measure the voltage between each phase and N on the noise filter PCB.
Result:
The measured voltages MUST be 230 V AC ± 10%.
Summary of Contents for Sky Air Advance RZA200D7Y1B
Page 1: ...Service manual Sky Air Advance series RZA200D7Y1B RZA250D7Y1B ...
Page 190: ......
Page 191: ......
Page 192: ...ESIE19 13A 2020 05 Copyright 2020 Daikin Verantwortung für Energie und Umwelt ...