Test Operation
Si39-406
90
General Information
Image of operation in the case of A
Image of operation in the case of B
Image of operation in the case of A and B
(V3081)
Power consumption
Rated power consumption
80 % of rated power consumption
70 % of rated power consumption
60 % of rated power consumption
40 % of rated power consumption
Forced thermostat OFF
(Fan operation)
Demand level 1 instructing
Power consumption set by
"Demand 1 level setting".
Demand level 2 instructing Demand level 3 instructing
The power
consumption during
the demand level 1
instructing can be
set with the
"Demand 1 level
setting".
("70 % of rated
power consumption"
has been set at
factory.)
(V3082)
The power consumption set with "Demand 1 level setting".
When the
"Continuous demand
setting" is set to ON
("OFF" has been set
at factory.) , the
power consumption
can be set with the
"Demand 1 level
setting". ("70 % of
rated power
consumption" has
been set at factory.)
Power consumption
Rated power consumption
80 % of rated power consumption
70 % of rated power consumption
60 % of rated power consumption
40 % of rated power consumption
Forced thermostat OFF
(Fan operation)
(V3083)
The power consumption set with "Demand 1 level setting".
H
Demand level 2 instructing
H
Demand level 3 instructing
The power
consumption can be
set with the
"Demand 1 level
setting". ("70 % of
rated power
consumption" has
been set at factory.)
H
During continuous demand operation,
when the external demand instruction is
received repeatedly, the instruction with
higher demand level has the precedence.
Power consumption
Rated power consumption
80 % of rated power consumption
70 % of rated power consumption
60 % of rated power consumption
40 % of rated power consumption
Forced thermostat OFF
(Fan operation)
Summary of Contents for REYQ96MTJU
Page 1: ...Design Installation Testing Instruction R410A Heat Recovery 60Hz REYQ96MTJU Si39 406...
Page 6: ...Si39 406 iv Table of Contents...
Page 34: ...Installation Si39 406 28 General Information Flaring Procedure...
Page 68: ...Installation Si39 406 62 General Information Caution Caution label 3P124617 4P124614...
Page 114: ...Appendix Si39 406 108 General Information 3P135887 1...
Page 126: ...Appendix Si39 406 120 General Information 7 8 3 BS Unit BSVQ36MVJ BSVQ60MVJ 4D045338...
Page 128: ...Appendix Si39 406 122 General Information 7 9 2 Field Wiring REYQ96MTJU 3D042647A...
Page 156: ...Refrigerant Piping Si39 406 150 Installation Manual REYQ96MTJU...
Page 158: ...Refrigerant Piping Si39 406 152 Installation Manual REYQ96MTJU...
Page 230: ...Precautions for New Refrigerant R410A Si39 406 224 Precautions for New Refrigerant R410...
Page 236: ...375 Park Avenue Suite 3308 New York N Y 10152 info daikinac com www daikinac com...