11 Disposal
Installation manual
10
40R2V1B
Daikin room air conditioner
3P482320-13U – 2021.03
Air inlet/outlet
Check that the air inlet and outlet of the unit is NOT
obstructed by paper sheets, cardboard, or any other
material.
There are NO
missing phases
or
reversed phases
.
The
refrigerant pipes
(gas and liquid) are thermally
insulated.
Drainage
Make sure drainage flows smoothly.
Possible consequence:
Condensate water might drip.
The system is properly
earthed
and the earth terminals
are tightened.
The
fuses
or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The
power supply voltage
matches the voltage on the
identification label of the unit.
The specified wires are used for the
interconnection
cable
.
The indoor unit receives the signals of the
user interface
.
There are NO
loose connections
or damaged electrical
components in the switch box.
The
insulation resistance
of the compressor is OK.
There are NO
damaged components
or
squeezed
pipes
on the inside of the indoor and outdoor units.
There are NO
refrigerant leaks
.
The correct pipe size is installed and the
pipes
are
properly insulated.
The
stop valves
(gas and liquid) on the outdoor unit are
fully open.
10.2
To perform a test run
Prerequisite:
Power supply MUST be in the specified range.
Prerequisite:
Test run may be performed in cooling or heating
mode.
Prerequisite:
Test run should be performed in accordance with the
operation manual of the indoor unit to make sure that all functions
and parts are working properly.
1
In cooling mode, select the lowest programmable temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.
2
When the test run is finished, set the temperature to a normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.
3
The system stops operating 3 minutes after the unit is turned
OFF.
10.2.1
To perform a test run using the user
interface
1
Press
to switch the system on.
2
Press
and
simultaneously.
3
Press
, select
and press
.
Result:
Test run operation will stop automatically after about
30 minutes.
4
To stop operation sooner, press
.
11
Disposal
NOTICE
Do NOT try to dismantle the system yourself: dismantling
of the system, treatment of the refrigerant, oil and other
parts MUST comply with applicable legislation. Units
MUST be treated at a specialised treatment facility for
reuse, recycling and recovery.
12
Technical data
▪ A
subset
of the latest technical data is available on the regional
Daikin website (publicly accessible).
▪ The
full set
of latest technical data is available on the Daikin
Business Portal (authentication required).
12.1
Wiring diagram
The wiring diagram is delivered with the unit, located inside of
the outdoor unit (bottom side of the top plate).
12.1.1
Unified wiring diagram legend
For applied parts and numbering, refer to the wiring diagram on the
unit. Part numbering is by Arabic numbers in ascending order for
each part and is represented in the overview below by "*" in the part
code.
Symbol
Meaning
Symbol Meaning
Circuit breaker
Protective earth
Connection
Protective earth (screw)
,
Connector
A
Rectifier
Earth
Relay connector
Field wiring
Short-circuit connector
Fuse
Terminal
INDOOR
Indoor unit
Terminal strip
OUTDOOR
Outdoor unit
Wire clamp
Residual current
device
Symbol
Colour
Symbol
Colour
BLK
Black
ORG
Orange
BLU
Blue
PNK
Pink
BRN
Brown
PRP, PPL
Purple
GRN
Green
RED
Red
GRY
Grey
WHT
White
YLW
Yellow
Symbol
Meaning
A*P
Printed circuit board
BS*
Pushbutton ON/OFF, operation
switch
BZ, H*O
Buzzer
C*
Capacitor