Daikin EWLD-J Installation, Operation And Maintenance Manual Download Page 17

 

 

D-EIMWC01008-16_03EN - 17/35 

In  cases  where  the  installation  is  subject  to  compliance  with  special  sound  requirements,  it  may  be  necessary  to  use 
additional noise attenuation devices, it is necessary to isolate the unit from its base with extreme care, correctly applying  
the anti-vibration elements (supplied as optional). Flexible joints must be installed on the water connections, as well.  
 

5.5 

Water piping 

Piping must be designed with the lowest number of elbows and the lowest number of vertical changes of direction. In this 
way, installation costs are reduced considerably, and system performance is improved.

 

The water system must have: 
1.  Anti-vibration mountings to reduce transmission of vibrations to the structures.  
2.  Isolating valves to isolate the unit from the water system during maintenance.  
3.  To protect the unit, the BPHE must be protected  against freezing by continuous monitoring of the water flow in the 

BPHE by a flow switch. In most cases, on site, the flow switch is set to generate an alarm only when the water pump 
turns off and the water flow drops to zero. It is recommended to adjust the flow switch to produce a "Water Leakage 
Alarm" when the water flow reaches the minimum value of the flow  allowable (see table 1); in this case the BPHE is 
protected against freezing and the flow switch can detect the clogging of the water filter. 

4.  Manual or automatic air venting device at the system highest point and drain device at the system lowest point.  
5. 

Neither the BPHE nor the heat recovery device must be positioned at the system’s highest point. 

6.  A suitable device that can maintain the water system under pressure (expansion tank, etc.). 
7.  Water temperature and pressure indicators to assist the operator during service and maintenance.  
8.  A filter or device that can remove particles from the fluid. The use of a filter extends the life of the BPHE and pump and 

helps to keep the water system in a better condition. 

The water filter must be installed as close as possible to the 

unit

. If the water filter is installed in another part of the water system, the Installer  must guarantee the cleaning of the 

water pipes between the water filter and the BPHE. 
Recommended maximum opening for strainer mesh is: 

 

0.87 mm (DX S&T) 

 

1.0 mm (BPHE) 

 

1.2 mm (Flooded) 

Precautions for correct use: 
9.  BPHE  has  an  electrical  resistance  with  a  thermostat  that  ensures  protection  against  water  freezing  at  ambient 

temperatures as low as -18°C. 
All the other water piping/devices outside the unit must therefore be protected against freezing.  

10. The heat  recovery device must be emptied of  water during the winter season, unless an ethylene glycol mixture in 

appropriate percentage is added to the water circuit.  

11. If  case  of  unit  substitution,  the  entire  water  system  must  be  emptied  and  cleaned  before  the  new  unit  is  installed. 

Regular tests and proper chemical treatment of water are recommended before starting up the new unit.  

12. If glycol is added to the water system as anti-freeze protection, pay attention to the fact that suction pressure will be 

lower, the unit performance will be lower and water pressure drops will be greater. All unit-protection systems, such as 
anti-freeze, and low-pressure protection will have to be readjusted. 

13. Before insulating water piping, check that there are no leaks. The complete hydraulic circuit must be insulated to prevent 

condensation and reduced refrigeration capacity. Protect the water pipes from frost during winter (using for example a 
glycol solution or a heating cable). 

14. Check that the water pressure does not exceed the design pressure of the water side heat exchangers. Instal l a safety 

valve on the water pipe downstream of the BPHE. 

 

5.5.1 

Water piping installation procedure 

 
The units are equipped  with a water inlet and  water outlet for connection to a chiller water circuit. This circuit must be 
provided by a licensed technician and must comply with all relevant European and national regulations. 
 

 

If air or dirt gets in the water circuit, problems may occur. Therefore, always take into account the 
following when connecting the water circuit. 

1. 

Use clean pipes only. 

2. 

Hold the pipe end downwards when removing burrs. 

3. 

Cover the pipe end when inserting it through a wall so that no dust and dirt enter

 

 
1.  Preparing the unit for connection to the water circuit. A box containing Victaulic

®

 couplings and a filter is 

delivered with the unit. 

 

Summary of Contents for EWLD-J

Page 1: ...structions REV 03 Date 04 2021 Supersedes D EIMWC01008 16_02EU Installation Operation and Maintenance Manual EWWD EWLD J EWWH EWLH J EWWS EWLS J Installation Operation and Maintenance Manual D EIMWC01...

Page 2: ...GUIDELINES FOR REMOTE CONDENSER APPLICATION EWLD J EWLH and EWLS versions 22 6 1 Installation information for condenserless units 22 6 1 1 Precautions when handling piping 22 6 1 2 Leak test and vacu...

Page 3: ...alve Condenser Shut off valve Filter drier Shut off valve charge valve Solenoid valve Liquid indicator 1 2 3 4 5 6 7 8 Control equipment High Pressure Switch 21 0bar Pressure Transducer Temperature Tr...

Page 4: ...EWLH80J SS 190J SS EWLS110J SS 270J SS Label Identification Figure 2 Description of the labels applied to the electrical panel 1 Unit nameplate data 5 Manufacturer s logo 2 Lifting instructions 6 Eme...

Page 5: ...el 14 check that the unit has been grounded correctly before starting it 15 install the machine in a suitable area in particular do not install it outdoors if it is intended for use indoors 16 do not...

Page 6: ...sfers heat to the water An expansion valve which allows the pressure of condensed liquid refrigerant to be reduced from condensation pressure to evaporation pressure A water cooled evaporator where th...

Page 7: ...9 31 7 70 50 13 18 69 20 69 7 2 26 12 4 43 32 7 92 51 13 51 70 21 16 6 2 34 13 4 58 33 8 15 52 13 85 71 21 64 5 2 43 14 4 73 34 8 39 53 14 20 72 22 13 4 2 53 15 4 88 35 8 63 54 14 55 73 22 62 3 2 62 1...

Page 8: ...a and R513A According to the standard EN 378 1 2016 any refrigerant system that contains R134a or R513A can be installed without any restriction in open air or machinery rooms Anyway the building owne...

Page 9: ...and including the charge and safety classification of the refrigerant used shall be conducted to determine whether it is necessary to place the refrigerating system in a separate refrigeration machine...

Page 10: ...gerants heavier than air and at the highest point for refrigerants lighter than air Detectors shall be continuously monitored for functioning In the case of a detector failure the emergency sequence s...

Page 11: ...ndensing atmosphere may damage electronic components 4 2 Operation The Daikin EWWD J EWLD J EWWH J EWLH J EWWS J EWLS J packaged water cooled water chillers are designed for indoor installation and us...

Page 12: ...D EIMWC01008 16_03EN 12 35 4 2 2 Operation range EWWD J 1 Operation with Glycol below 4 C Evap LWT EWLD J 1 Operation with Glycol below 4 C Evap LWT...

Page 13: ...vap LWT 2 Option111 and operation with Glycol below 4 C Evap LWT 3 Option111 4 Option 111 Option 189 5 Option 189 EWLH J 1 Operation with Glycol below 4 C Evap LWT 2 Option111 and operation with Glyco...

Page 14: ...D EIMWC01008 16_03EN 14 35 EWWS J 1 Operation with Glycol below 4 C Evap LWT EWLS J 1 Operation with Glycol below 4 C Evap LWT...

Page 15: ...re 3 Lifting When handling the unit take into account the following 1 List the unit preferably with a crane and belts in accordance with the instructions on the unit The length of the ropes 1 to be us...

Page 16: ...x the unit on a concrete base with anchor bolts 1 Anchor bolt 2 Washer 3 Rubber plate 4 Row cork or rubber sheet 5 Ground 6 Concrete floor 7 Ditch Figure 4 Unit Levelling Fix anchor bolts into the con...

Page 17: ...antee the cleaning of the water pipes between the water filter and the BPHE Recommended maximum opening for strainer mesh is 0 87 mm DX S T 1 0 mm BPHE 1 2 mm Flooded Precautions for correct use 9 BPH...

Page 18: ...ection pipes prior the operation see figure Connecting the filter The filter kit supplied with the unit must be installed in front of the evaporator water inlet by means of the supplied Victaulic coup...

Page 19: ...nge as specified in the table below and a minimum water volume is required in the system Model Minimum water flow l min Maximum water flow l min EWWD120J EWLD110J EWWH090J EWLH080J EWWS120J EWLS110J 1...

Page 20: ...anti freeze electrical resistance which provides adequate anti freeze protection at temperatures as low as 18 C However unless the heat exchangers are completely empty and cleaned with anti freeze so...

Page 21: ...gram terminals L1 L2 and L3 5 Supply water to the evaporator and verify if waterflow is within the limits as given in the table under Water charge flow and quality 6 The piping must be completely purg...

Page 22: ...e used For copper to copper joints use a phos copper solder with 6 to 8 silver content A high silver content brazing rod must be used for copper to brass or copper to steel joints Only use oxy acetyle...

Page 23: ...must be between 3 and 8 K c Verify the oil sight glass Level must be within the sight glass d Verify the liquid line sight glass It should be sealed and not indicate moisture in the refrigerant e As l...

Page 24: ...D EIMWC01008 16_03EN 24 35 Figure 5 Condenser located with no elevation difference Figure 6 Condenser located above the unit...

Page 25: ...alves etc Table 2 shows the equivalent length of pipe for various nonferrous valves and fittings Follow these steps when calculating line size 1 Start with an initial approximation of equivalent lengt...

Page 26: ...oling may be affected In these situations insulate the liquid lines Reference for liquid line sizing is shown in Table 3 It has to be used for reference only for circuit working with condensing temper...

Page 27: ...234ze R513A 6 2 4 Oil charge In remote condenser application the oil charge into the compressor has to take into account that a percentage of oil around 1 is usually mixed into the refrigerant so some...

Page 28: ...dards for industrial environments Therefore it is not intended for use in residential areas e g installations where the product is connected to a low voltage public distribution system Should this pro...

Page 29: ...al areas e g installations where the product is connected to a low voltage public distribution system Should this product need to be connected to a low voltage public distribution system specific addi...

Page 30: ...operating manual and the wiring diagram in order to understand start up sequence operation shutdown sequence and operation of all the safety devices During the unit s initial start up phase a technici...

Page 31: ...sure that the work area is properly ventilated before working on the refrigerant circuit or before welding brazing or soldering work ensure that the leak detection equipment being used is non sparking...

Page 32: ...be read on a daily basis thus keeping high observation standards 4 Replace the oil filter when the pressure drop across it reaches 2 0 bar 5 Check for any dissolved metals TAN Total Acid Number 0 10...

Page 33: ...unbalance between phases exceeding 3 The unit must stay turned off until the electrical problem has been solved 4 No safety device either mechanical electrical or electronic must be disabled or overri...

Page 34: ...ed inside the electrical panel Fill in with indelible ink the refrigerant charge label supplied with the product as following instructions Any refrigerant charge for each circuit 1 2 3 added during co...