4 Unit installation
Installation manual
9
EWAA011~016DA + EWYA009~016DA
Packaged air-cooled water chillers
and packaged air to water heat pumps
4P620240-1 – 2020.06
3
Remove the slings, and dispose of them.
4
Fix the unit to the installation structure.
6× M12
4.2.3
To provide drainage
INFORMATION
If necessary, you can use a drain pan (field supply) to
prevent drain water from dripping.
NOTICE
If the unit CANNOT be installed fully level, always make
sure that the inclination is towards the backside of the unit.
This is required to guarantee proper drainage.
NOTICE
If drain holes of the outdoor unit are covered by a mounting
base or by floor surface, raise the unit to provide a free
space of more than 150 mm under the outdoor unit.
≥150 mm
Drain holes (dimensions in mm)
A
171
300
758
43
48
288
451
613
776
408
414
349
214
111
480~490
107
148
B
B
B
406
C
D
F
=
E
A
Discharge side
B
Distance between anchor points
C
Bottom frame
D
Knockout hole for snow
E
Drain hole for safety valve
F
Drain holes
Snow
In regions with snowfall, snow might build up and freeze between the
heat exchanger and the casing of the unit. This might decrease the
operating efficiency. To prevent this:
1
Remove the knockout hole (a) by tapping on the attachment
points with a flat head screwdriver and a hammer.
a
2
Remove the burrs, and paint the edges and areas around the
edges using repair paint to prevent rusting.
NOTICE
When making knockout holes, do NOT damage the casing
and underlying piping.
4.2.4
To install the discharge grille
1
Insert the hooks. To prevent breaking the hooks:
▪ First insert the bottom hooks (2×).
▪ Then insert the top hooks (2×).
2
Insert and fix the screws (4×)(delivered as accessory).
1
2
2
1
4 N • m
4×
T25
4.3
Opening and closing the unit
4.3.1
To open the outdoor unit
DANGER: RISK OF ELECTROCUTION