Troubleshooting
ESIE11-02
3–26
3
1
3
4
5
4.3
General Repair Procedures
Refrigeration circuit
repairs
To carry out refrigeration circuit repairs, proceed as follows:
For more information on the general repair procedures for R-407C, refer to the Service Manual for
products using refrigerant R-407C.
All refrigeration work has to be carried out by a licensed refrigeration engineer, and it has to comply
with all relevant European and national regulations.
Electrical circuit
repairs
To carry out electrical circuit repairs, proceed as follows:
All electrical work has to be carried out by a licensed electrical engineer, and it has to comply with all
relevant European and national regulations.
Step
Action
1
Recover the refrigerant from the unit.
It is strictly forbidden to release refrigerant into the atmosphere during service or repair
jobs.
2
Carry out the repair according to the normal procedure.
There are no special procedures for the replacement of refrigeration parts. See the
general Daikin air-conditioning service manual for more information on the standard
practice of refrigeration works.
3
Pressurize the system. Make sure there are no leaks.
4
Charge with the proper amount of refrigerant.
Step
Action
1
Measure all that is needed to locate the defective parts of the system.
2
Switch OFF the main power supply.
3
Carry out the repair according to standard procedures.
4
Switch ON the power supply.
5
Verify the proper operation of the replaced part by measurements.
Summary of Contents for EUWY 24KBZW1 Series
Page 2: ......
Page 8: ...ESIE11 02 vi Table of Contents 3 1 4 5...
Page 10: ...Introduction ESIE11 02 viii 3 1 4 5...
Page 12: ...ESIE11 02 1 2 Part 1 System Outline 3 1 1 5...
Page 86: ...Wiring Layout ESIE11 02 1 76 Part 1 System Outline...
Page 88: ...ESIE11 02 2 2 Part 2 Functional Description 3 1 2 5...
Page 128: ...The Digital Controller ESIE11 02 2 42 Part 2 Functional Description 3 1 2 4 5...
Page 130: ...ESIE11 02 3 2 Part 3 Troubleshooting 3 1 3 5...
Page 168: ...ESIE11 02 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 198: ...Test Run and Operation Data ESIE11 02 4 32 Part 4 Commissioning and Test Run 3 1 4 5...
Page 200: ...ESIE11 02 5 2 Part 5 Maintenance 3 1 5...
Page 210: ...ESIE11 02 4 Index 3 1 4 5...