Pre-Test Run Checks
ESIE11-02
4–4
Part 4 – Commissioning and Test Run
3
1
4
5
1.2
General Checks
Checklist
The table below contains the general checklist.
Step
Check whether...
1
There is external damage.
2
The unit is properly supported and/or has a proper foundation.
3
The unit is installed horizontally with a deviation of maximum 1°.
4
Anti-vibration pads are required.
5
Is the chiller of the type EUWY*5-24KBZW1?
■
When yes, go to step 6.
■
When no, go to step 8.
6
There is a drain possibility for condensed water.
7
A heater tape is placed inside the drain system. This is necessary to prevent ice accumu-
lation and possible blockage during wintertime.
8
Check for remaining metal dust of burrs. Metal dust or burrs from grinding or drilling in the
metal parts during construction facilitates the rust process and shortens the lifetime of the
unit.
9
The operator has received the operation manual.
10
The installer has received the installation manual.
11
The air volume over the coil is adequate; there is no blockage (from paper, plastic...) or air
short circuit due to wrong positioning.
Summary of Contents for EUWAB10KBZW1
Page 2: ......
Page 8: ...ESIE11 02 vi Table of Contents 3 1 4 5...
Page 10: ...Introduction ESIE11 02 viii 3 1 4 5...
Page 12: ...ESIE11 02 1 2 Part 1 System Outline 3 1 1 5...
Page 86: ...Wiring Layout ESIE11 02 1 76 Part 1 System Outline...
Page 88: ...ESIE11 02 2 2 Part 2 Functional Description 3 1 2 5...
Page 128: ...The Digital Controller ESIE11 02 2 42 Part 2 Functional Description 3 1 2 4 5...
Page 130: ...ESIE11 02 3 2 Part 3 Troubleshooting 3 1 3 5...
Page 168: ...ESIE11 02 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 198: ...Test Run and Operation Data ESIE11 02 4 32 Part 4 Commissioning and Test Run 3 1 4 5...
Page 200: ...ESIE11 02 5 2 Part 5 Maintenance 3 1 5...
Page 210: ...ESIE11 02 4 Index 3 1 4 5...