Typical workflow
Mounting the outdoor unit typically consists of the following stages:
1
Providing the installation structure.
2
Installing the outdoor unit.
3
Providing drainage.
4
Installing the discharge grille.
5
Protecting the unit against snow and wind by installing a snow cover and baffle
plates. See
"7.1 Preparing the installation site"
7.3.2 Precautions when mounting the outdoor unit
INFORMATION
Also read the precautions and requirements in the following chapters:
▪
"2 General safety precautions"
▪
"7.1 Preparing the installation site"
7.3.3 To provide the installation structure
Check the strength and level of the installation ground so that the unit will not
cause any operating vibration or noise.
Fix the unit securely by means of foundation bolts in accordance with the
foundation drawing.
NOTICE
Level.
Make sure the unit is level. Recommended:
Use 4 sets of M12 anchor bolts, nuts and washers. Provide at least 150 mm of free
space below the unit. Additionally, make sure the unit is positioned at least
100 mm above the maximum expected level of snow.
Anchor points
800
(mm)
479