Charge the system with nitrogen gas up to a gauge pressure of at least
200 kPa (2 bar). It is recommended to pressurize to 3000 kPa (30 bar) in order
to detect small leaks.
2
Check for leaks by applying the bubble test solution to all connections.
3
Discharge all nitrogen gas.
8.3.4 To perform vacuum drying
Connect the vacuum pump and manifold as follows:
a
d
j
b
f
e
c
g h i
h
a
Pressure meter
b
Gauge manifold
c
Low pressure valve (Lo)
d
High-pressure valve (Hi)
e
Charging hoses
f
Vacuum pump
g
Service port
h
Valve lids
i
Gas stop valve
j
Liquid stop valve
1
Vacuum the system until the pressure on the manifold indicates −0.1 MPa
(−1 bar).
2
Leave as is for 4-5 minutes and check the pressure:
If the pressure…
Then…
Does not change
There is no moisture in the system.
This procedure is finished.
Increases
There is moisture in the system. Go
to the next step.
3
Vacuum the system for at least 2 hours to a manifold pressure of −0.1 MPa
(−1 bar).
4
After turning the pump OFF, check the pressure for at least 1 hour.
5
If you do NOT reach the target vacuum or CANNOT maintain the vacuum for
1 hour, do the following:
▪
Check for leaks again.
▪
Perform vacuum drying again.
NOTICE
Make sure to open the stop valves after installing the refrigerant piping and
performing vacuum drying. Running the system with the stop valves closed may
break the compressor.
Summary of Contents for EHVZ04S18EA6V
Page 269: ......
Page 270: ......
Page 271: ......
Page 272: ...4P629093 1A 2021 11 Copyright 2020 Daikin Verantwortung für Energie und Umwelt ...