12
|
Commissioning
Installer reference guide
213
EWSAH/X06D
Daikin Altherma 3 WS
4P675764-1 – 2022.04
1
Set the user permission level to Installer. See
134].
—
2
Go to [A.2]:
Commissioning
>
Actuator test run
.
3
Select a test from the list.
Example:
Pump
.
4
Select
OK
to confirm.
Result:
The actuator test run starts. It stops automatically when
ready (±30 min).
To stop the test run manually:
—
1
In the menu, go to
Stop test run
.
2
Select
OK
to confirm.
Possible actuator test runs
▪
Backup heater 1
test (3 kW capacity, only available when no current sensors
are used)
▪
Backup heater 2
test (6 kW capacity, only available when no current sensors
are used)
▪
Pump
test
INFORMATION
Make sure that all air is purged before executing the test run. Also avoid disturbances
in the water circuit during the test run.
▪
Shut off valve
test
▪
Diverter valve
test (3-way valve for switching between space heating and
tank heating)
▪
Bivalent signal
test
▪
Alarm output
test
▪
C/H signal
test
▪
DHW pump
test
▪
Backup heater phase 1
test (3 kW capacity, only available when current
sensors are used)
▪
Backup heater phase 2
test (3 kW capacity, only available when current
sensors are used)
▪
Backup heater phase 3
test (3 kW capacity, only available when current
sensors are used)
▪
Water loop valve
test
To perform a current sensor phase check
To make sure that the current sensors measure the current of the correct phase,
perform a current sensor phase check. This can be done using the backup heater
actuator tests.
Note:
Make sure that
Power consumption control
is set to
Current
sensor
([4‑08]=3). See
195].
1
Set the user permission level to Installer. See
134].
—