9 Commissioning
NOTICE
Make sure both air purge valves (one on the magnetic filter and one on the backup
heater) are open.
All automatic air purge valves must remain open after commissioning.
INFORMATION
Protective functions – "Installer-on-site mode"
. The software is equipped with
protective functions, such as room antifrost. The unit automatically runs these
functions when necessary.
During installation or service this behaviour is undesired. Therefore, the protective
functions can be disabled:
▪
At first power-on:
The protective functions are disabled by default. After 12 h
they will be automatically enabled.
▪
Afterwards:
An installer can manually disable the protective functions by setting
[9.G]:
Disable protections
=
Yes
. After his work is done, he can enable the
protective functions by setting [9.G]:
Disable protections
=
No
.
9.1 Overview: Commissioning
This chapter describes what you have to do and know to commission the system
after it is installed and configured.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing an air purge.
3
Performing a test run for the system.
4
If necessary, performing a test run for one or more actuators.
5
If necessary, performing an underfloor heating screed dryout.
9.2 Precautions when commissioning
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50 hours before reaching smooth operation and
stable power consumption.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.