Network Terminal Installation, Operation, and Maintenance Instructions
P/N 8040375G001
4-3
C
HELIX TECHNOLOGY CORPORATION
-
TI
CRYOGENICS
Rough Valve Map Example Procedure
Use the following procedure to create a rough valve map as shown in
Figure 4-2.
NOTE: A minimum of 2 pumps per map is required.
1. Press SERVICE, then press 9 9. The display shows serial
number and the software version.
NOTE: The TERMINAL ID #XX in step 2 is present only if the NetLink
option is installed.
2. Press Next to display TERMINAL ID #XX.
3. Press Next. The display shows number of pumps on network.
4. Press Next. The display reads PASSWORD?
5. Press Enter, then Next. The display reads REGEN LOCK OFF.
6. Press Next. The display reads ROUGH VALVE MAP.
7. Press Enter. The display reads MAP A.
8. Press Enter.
9. Press 00 Enter, 01 Enter, 02 Enter, Enter. Map A is complete.
The display now reads MAP B.
10. Press Enter.
11. Press 05 Enter, 08 Enter, 06 Enter, Enter. Map B is complete.
The display now reads MAP C.
12. Press Enter.
13. Press 03 Enter, 04 Enter, 07 Enter, 09 Enter, Enter. Map C is
complete.
Summary
A roughing map describes all of the pumps that share a roughing manifold.
Up to five roughing maps can be set up on a multi-pump On-Board System
through the Network Terminal.
If several Cryopumps on the same manifold begin FastRegen, then they
must all be started at the same time. The Network Terminal coordinates the
simultaneous starting of pumps through Regeneration Groups as
described within this section.