64
8.4
CONNECTION OF THE PRESSURE LINE
NOTE:
All activities may only be carried out by professional and knowledgeable personnel
who have been sufficiently informed by studying the operating instructions in-depth;
This personnel must have read and understood this operating manual;
The pressure line establishes the connection to the on-site installation and regulates with the pump
switching machine the pressure - and flow-dependent supply of service water.
• For the connection of the pressure line, we recommend a dimension-appropriate 1“ inner diameter
tank hose with the required connections and an additional ball tap, thus:
- can be compensated for on-site assembly tolerances;
- reduce possible vibration and noise transmissions;
- the pressure line can be shut off at any time;
- required work on the Conel Stream can be performed with less effort.
•
Connect the tank hose connection (1“ IG) to the 1“ AG of the pump switcher and ensure a fixed and
leakage-free connection (see Figure 8.4.1);
• If you do not use an armored hose to connect the Conel Stream, make sure that the piping and
connection are exactly in the flight tom Conel Stream - Anschluss and have no tension - leakage
possible;
8.5
CONNECTION OF THE EMERGENCY OVERFLOW
In the unlikely event that too much drinking water is discharged in the Conel Stream and overflows ,this
amount of water can be discharged in an orderly manner via the emergency overflow of Conel Stream
into the public sewer network or into a lifting system.
•
In order to ensure a proper operation of the emergency overflow if necessary, the following measu
-
res are mandatory:
-
Connect the emergency overflow of the Conel Stream (DN70) at least with a DN 70 pipe (drain)
and initiate it into the public channel or a system.
-
Make sure that the flow is a vertical drop distance of min. 50cm before an elbow is placed - better
flow in the drop;
- We recommend the installation of a dimension-appropriate siphon as an odor closure to the
sewer network.
NOTE:
The operation of an Conel Stream requires a room with integrated ground runoff on
the construction side.
If the device is installed below the backlog level (x), the overflow must be discharged
into a lifting system that discharges the water above the backlog plane into the chan-
nel via a pipe loop. Make sure that the lifting system is sufficiently dimensioned with a
conveying capacity of at least 3m3/h.
(x) Backlog level: Is the level to which an overloaded sewer network can accumulate
– usually corresponds to the respective road level, in order to be sure, please contact
the responsible building authority.
Summary of Contents for KBN COSSTS5
Page 1: ...1 TRINKWASSERTRENNSTATION DRINKING WATER SPLITTING STATION D GB STREAM...
Page 2: ...2...
Page 3: ...3 Technische nderungen vorbehalten F r Druckfehler wird keine Haftung bernommen...
Page 41: ...41...
Page 78: ...78...
Page 79: ...79...