Condeco 10.1’’ Room Screen Mounting Instructions
Screen Commission Pre-requisites
If screen commissioning has been purchased as part of the installation, you will need to
ensure the following pre-requisites are in place prior to an engineer attending site:
Screen back plates fitted in position to the location requirements.
Pre terminated network cable with RJ45 connector at the screen. The terminating cable
should be approximately 20cm from the back plate entry to the connector.
The provided network cable should be patched and tested as operational on the
network.
The network connection provided must be capable of supplying POE to the screen either
from the switch or by the use of an inline injector somewhere between the screen and
the network switch. These should be in place and powered. We recommend using a
Netgear POE switch.
The network point should be tested to ensure routing of http traffic port 80 is available to
the server that the Condeco software is to be installed on.
If the use of static IP addresses is required these should be pre-allocated and the
engineer advised of the IP addresses and the meeting room/screens they are to be used
on.
On attendance, the engineer will mount each screen to the pre installed back plates,
program any static IP addresses required, commission the screens to the software and test
the functionality.