12.3.5
Strip the tube/subunit up to the mark.
12.3.6
Insert the tube/subunit in the grooves of the tube/
subunit holder area. Cut a piece of the orange tubing of
30mm (1.18’’). Press the piece of orange tubing in the groove
on top of the tube/subunit.
Note: place the end of the orange tube/subunit at the start
of the groove. This makes it easier to remove the orange
tubing.
12.3.7
Re-install the protection cover over the tube/sub
-
unit holder area. Position the plastic cover with the openings
over the snap features and push until it snaps.
12.3.8
Route the fibers to the selected tray. See chapter
13 for detailed instructions concerning fiber routing.
12.
Install drop cable
Drop cables can be installed in all positions at the front side
or in the positions in the two seal segments left and right at
the back side.
12.3.1
Remove the top gel seal segment and the dummy
plugs. Click the CTU in the plastic CTU holder as shown.
12.3.2
If there are unused positions in the gel seal
segment, place a dummy plug in these positions (4 in
example above).
12.3.3
Place the second gel seal segment on top of the
cables. Make sure the corners of the gel seal segment are
properly inserted under the protrusions of the gel seal area.
12.3.4
Position the tube/subunit on top of the groove and
mark the tube/subunit at the point indicated with the lines.
The grooves in the tube/subunit holder area are designed for
tube/subunits with a maximum Ø of 2.4mm.