ADCP-96-167 • Issue 5 • July 2016
Page 55
© 2016, CommScope, Inc.
Figure 51. Securing Cable Slack to Cabinet
16. When all the cables are installed, tighten the compression nut to secure the MPO
cables at the cable entry/exit hole as shown in
.
17. Repeat this procedure as needed for the remaining entry/exit hole.
18. Close the swingframe and the cabinet door when all the MPO cables have been
installed.
Note:
The two metal spacers that are included with the compression fitting will
prevent the compression nut from being overtightened.
Note:
If the remaining entry/exit hole is not needed, verify that the compression
) is installed in the compression fitting. Then tighten
the compression nut until it bottoms against the spacers.
MPO
CABLES
CABLE
TIE
24357-A