Installation check list: Antenna
7-2
Chapter 7: Installation check
98-146706-A
7.1
Installation check list: Antenna
Step
Task
Further information
Done
1.
Check that the antenna is free of obstructions.
See
2.
Make sure there is sufficient space for access
through the service hatch.
3.
Make sure to maintain the vertical orientation
of the ADU center line.
4.
Check that the ADU is installed where
vibrations are limited to a minimum.
5.
Check that you programmed the blocking
zones correctly.
Blocking zones with azimuth and
and
To set up blocking zones (RX and TX)
6.
Make sure that the safety distance for radiation
hazard of 30 metres is kept.
Safe access to the ADU (radiation
7.
Check that the mounting height of the antenna
is in accordance with the ship’s min. roll period.
Ship motion and offset from the
8.
Make sure that the requirements for mast
foundation and height, including flatness,
gusset plates and distance from welding seams
are met.
9.
Make sure that the distances to radar, Inmarsat
systems, GPS receivers and other transmitters
are as required.
Interference from radar, GPS and
10.
Make sure that the drain tube is open and risk
for water intrusion is at a minimum.
Condensation, water intrusion and
11.
Check that the ADU is grounded correctly,
using the mounting bolts.
and
Table 7-1: Installation check list: Antenna