To verify the software update (ADU and ACU)
After completing the software update procedure, the ACU will perform a POST (Power On
Self Test). When the POST has finished, the green Pass/Fail LED on the front of the ACU
must become steadily green.
To verify the software update do as follows:
1. Verify that the Pass/Fail LED is not red nor flashing orange once every 2 seconds.
2. Wait until the Pass/Fail LED is green.
3. Verify that the software update has been completed successfully. You find the software
version number in the
DASHBOARD
window of the web interface.
Figure 8-7: Verifying software update