Chapter 5 — Starting and Operating Instructions
5-16
Part No. 750-184
J. CONTROL OPERATIONAL TEST AND CHECKS
Proper operation of the various controls should be verified and
tested when the boiler is initially placed into service, or whenever a
control is replaced. Periodic checks should be made thereafter in
accordance with a planned maintenance program.
The operating limit control may be checked by allowing steam
pressure or water temperature to increase until the burner shuts
down. Depending upon the load, it may be necessary to manually
increase the firing rate to raise steam pressure to the burner shut off
point. If the load is heavy, the header valve can be closed or
throttled until the pressure increases. Observe the steam gauge to
check the cut off pressure as the operating limit control shuts the
burner down. Slowly open the header valve to release steam
pressure and check the cut-in setting as the burner restarts. Check
the modulating control for the desired operating pressure range. See
Chapter 6 for instructions on the adjustment of controls.
The water temperature on a hot water boiler that may be operating
at less than full load may be raised by manually increasing the firing
rate until the burner shuts down through the action of the operating
limit control. Observe the thermometer to verify the desired settings
at the point of cut-out and again when the burner restarts. Return
the manual automatic switch to “automatic” and check the
modulating control for the desired temperature range. See Chapter
6 for instructions on the adjustment of the controls.
Check the proper operation and setting of the low-water cutoff (and
pump operating control, if used).
Proper operation of the flame failure device should be checked at
startup and at least once a week thereafter. Refer to Chapter 8 for
information on flame safety checks. Check the program relay’s
annunciation for any system failure. Observe the promptness of
ignition of the pilot flame and the main flame.
Check for tight shut-off of all fuel valves. Despite precautions and
strainers, foreign material may lodge under a valve seat and prevent
tight closure. Promptly correct any conditions that cause leakage.
Summary of Contents for CB Ohio Special 100 HP
Page 2: ...ii ...
Page 8: ...viii ...
Page 42: ...Chapter 2 Burner Operation and Control 2 22 Part No 750 184 ...
Page 116: ...Chapter 6 Adjustment Procedures 6 28 Part No 750 184 ...
Page 126: ...Chapter 8 Inspection and Maintenance 8 6 Part No 750 184 ...
Page 153: ...Chapter 9 Parts Part No 750 184 9 3 Insulated Front Head Model CB LE ...
Page 154: ...Chapter 9 Parts 9 4 Part No 750 184 Insulated Front Head Interior Model CB LE ...
Page 155: ...Chapter 9 Parts Part No 750 184 9 5 Insulated Inner Door Model CB OS ...
Page 156: ...Chapter 9 Parts 9 6 Part No 750 184 Insulated Rear Head CB LE ...
Page 157: ...Chapter 9 Parts Part No 750 184 9 7 Insulated Rear Head CB LE ...
Page 158: ...Chapter 9 Parts 9 8 Part No 750 184 Insulated Rear Head CB OS ...
Page 159: ...Chapter 9 Parts Part No 750 184 9 9 Dry Oven Model CB LE ...
Page 161: ...Chapter 9 Parts Part No 750 184 9 11 Motor Impeller Model CB LE ...
Page 162: ...Chapter 9 Parts 9 12 Part No 750 184 Front Head Linkage ...
Page 170: ...Chapter 9 Parts 9 20 Part No 750 184 Control Cabinet Hawk ICS ...
Page 171: ...Chapter 9 Parts Part No 750 184 9 21 Control Panel Standard ...
Page 172: ...Chapter 9 Parts 9 22 Part No 750 184 Entrance Box ...
Page 173: ...Chapter 9 Parts Part No 750 184 9 23 Front Head Electrical CB LE ...
Page 174: ...Chapter 9 Parts 9 24 Part No 750 184 Front Head Electrical CB LE ...
Page 175: ...Chapter 9 Parts Part No 750 184 9 25 Front Head Electrical CB OS ...
Page 176: ...Chapter 9 Parts 9 26 Part No 750 184 Front Head Electrical CB OS ...
Page 179: ...Chapter 9 Parts Part No 750 184 9 29 Heavy Oil Piping 60 Steam CB LE ...
Page 180: ...Chapter 9 Parts 9 30 Part No 750 184 Heavy Oil Piping 60 Steam CB LE SEE TABLE NEXT PAGE ...
Page 181: ...Chapter 9 Parts Part No 750 184 9 31 Common Oil Parts Heavy Oil ...
Page 182: ...Chapter 9 Parts 9 32 Part No 750 184 Side Mounted Air Compressor Piping ...
Page 183: ...Chapter 9 Parts Part No 750 184 9 33 Air Compressor Piping CB OS ...
Page 185: ...Chapter 9 Parts Part No 750 184 9 35 Light Oil Piping ...
Page 186: ...Chapter 9 Parts 9 36 Part No 750 184 Light Oil Air Piping Front Head ...
Page 187: ...Chapter 9 Parts Part No 750 184 9 37 Light Oil Air Piping Front Head PAGE 9 31 ...
Page 191: ...Chapter 9 Parts Part No 750 184 9 41 Gas Train 125 150 HP ...
Page 193: ...Chapter 9 Parts Part No 750 184 9 43 Gas Train 200 HP ...
Page 195: ...Chapter 9 Parts Part No 750 184 9 45 Steam Pressure Controls ...
Page 196: ...Chapter 9 Parts 9 46 Part No 750 184 Hot Water Temperature Controls ...
Page 197: ...Chapter 9 Parts Part No 750 184 9 47 Water Column ...
Page 198: ...Chapter 9 Parts 9 48 Part No 750 184 Water Column ...
Page 199: ...Chapter 9 Parts Part No 750 184 9 49 Fireside Gaskets CB LE ...
Page 200: ...Chapter 9 Parts 9 50 Part No 750 184 Fireside Gaskets CB OS ...