Section 2 — Installation
2-6
Part No. 750-363
Table 2-2 Model CFLC Water Chemistry Requirements
2.5 BOILER FLUSH
Cleaver-Brooks recommends cleaning in accordance with the recommendations of the boiler owner’s water treatment
company for each individual site. The boiler may be flushed with or without heat applied, as deemed appropriate by the
chemical treatment company. A traditional steam “Boil Out” is not required on Cleaver-Brooks hot water boilers.
Following are some general recommendations to help ensure long boiler life and efficient operation.
NOTE: these are recommendations only. The chemical treatment supplier should recommend a procedure based on
the site conditions and quality of water being used to fill the system.
If the entire system is being flushed THROUGH the boiler, weld slag and deposits from the piping system may settle in
the boiler. The boiler is typically a low velocity zone where these deposits tend to accumulate. The boiler should be
drained periodically during the flushing process to keep any deposit build up to a minimum. When the system flush is
complete, drain the boiler completely and open water side inspection ports for visual inspection. Any deposits should be
manually flushed out.
If the boiler is isolated during the system flush, or if this is an equipment replacement only where minimal amounts of
system piping have been replaced, there should be minimal manufacturing deposits inside the boiler and no boiler flush
is required.
To provide the longest life of the equipment it is recommended but not mandatory to chemically treat the boiler prior to
start-up. The owner’s water treatment company should determine needed course of action for each installation.
2.6 USING GLYCOL
The Model CFLC boiler may be operated with a solution of glycol and water. Where glycols are added, the
system must first be cleaned and flushed. Correct glycol selection and regular monitoring of the in-use
concentration and its stability is essential to ensure adequate, long-term freeze protection, including
protection from the effects of glycol-derived corrosion resulting from glycol degradation.
Note: Corrosion and sludge deposits in old systems must be removed
prior to installation of a new boiler.
Parameter
Limit
Means of control
Glycol
25-50%
Glycol fill/mixing station
pH
8.3 - 10.5
Buffering agent
Nitrates
50 ppm
Chemical additives
Sulfates
50 ppm
Chloride
< 250 ppm
Oxygen
< 0.1 ppm
Air separator/eliminator
Specific Conductivity
< 3500
m
mho/cm
Total Hardness
< 10 ppm
Softener
Table 2-3 Model CFLC Water Temperature Data (Non-Glycol)
Minimum inlet temp.
33
o
F
Maximum operating supply set point temp.
230
o
F
Maximum design temp.
250
o
F
Minimum supply set point temperature
130
o
F
Max allowable Delta T
100
o
F
Summary of Contents for ClearFire CFLC Series
Page 6: ...vi...
Page 14: ...Section 1 Introduction 1 8 Part No 750 363...
Page 16: ...Section 2 Installation 2 2 Part No 750 363...
Page 36: ...Section 2 Installation 2 22 Part No 750 363 Figure 2 13 Electrical Connections CFLC FALCON...
Page 38: ...Section 2 Installation 2 24 Part No 750 363...
Page 56: ...Section 3 Stack and Intake Vent Sizing and Installation 3 18 Part No 750 363...
Page 87: ...Section 6 Parts Part No 750 363 6 3 Figure 6 1 Boiler Mechanical Assembly CFLC 4000 5000...
Page 88: ...Section 6 Parts 6 4 Part No 750 363 Figure 6 2 Boiler Mechanical Assembly CFLC 6000 8000...
Page 95: ...Section 6 Parts Part No 750 363 6 11 Figure 6 10 Gas Train CFLC 6000 8000 optional 9 PPM NOx...
Page 97: ...Section 6 Parts Part No 750 363 6 13 Figure 6 12 Gas train CFLC 10000 12000 optional 9 PPM NOx...
Page 98: ...Section 6 Parts 6 14 Part No 750 363 Figure 6 13 Gas Train CFLC 4000 5000 Propane...
Page 99: ...Section 6 Parts Part No 750 363 6 15 Figure 6 14 Gas Train CFLC 6000 8000 Propane...
Page 100: ...Section 6 Parts 6 16 Part No 750 363 Figure 6 15 Gas Train CFLC 10000 12000 Propane...
Page 105: ...Section 6 Parts Part No 750 363 6 21 Figure 6 20 Control Panel...
Page 106: ...Section 6 Parts 6 22 Part No 750 363 Figure 6 21 Cables and Cable Harness...
Page 108: ...Section 6 Parts 6 24 Part No 750 363 Figure 6 23 Casing Insulation 4000 5000 cont d...
Page 109: ...Section 6 Parts Part No 750 363 6 25 Figure 6 24 Casing Insulation 6000 8000...
Page 110: ...Section 6 Parts 6 26 Part No 750 363 Figure 6 25 Casing Insulation 6000 8000 cont d...
Page 115: ...APPENDIX A Falcon Parameters...
Page 116: ......
Page 124: ......
Page 144: ......
Page 145: ...APPENDIX C Gas Valve Page C 3 Siemens Gas Valve Page C 25 Dungs Gas Valve CFLC 4000 5000...
Page 146: ......
Page 147: ...Appendix C Gas Valve C 3...
Page 148: ...Gas Valve Appendix C C 4...
Page 149: ...Appendix C Gas Valve C 5...
Page 150: ...Gas Valve Appendix C C 6...
Page 151: ...Appendix C Gas Valve C 7...
Page 152: ...Gas Valve Appendix C C 8...
Page 153: ...Appendix C Gas Valve C 9...
Page 154: ...Gas Valve Appendix C C 10...
Page 155: ...Appendix C Gas Valve C 11...
Page 156: ...Gas Valve Appendix C C 12...
Page 157: ...Appendix C Gas Valve C 13...
Page 158: ...Gas Valve Appendix C C 14...
Page 159: ...Appendix C Gas Valve C 15...
Page 160: ...Gas Valve Appendix C C 16...
Page 161: ...Appendix C Gas Valve C 17...
Page 162: ...Gas Valve Appendix C C 18...
Page 163: ...Appendix C Gas Valve C 19...
Page 164: ...Gas Valve Appendix C C 20...
Page 165: ...Appendix C Gas Valve C 21...
Page 166: ...Gas Valve Appendix C C 22...
Page 167: ...Appendix C Gas Valve C 23...
Page 168: ...Appendix C Gas Valve C 24...
Page 186: ...Appendix C Gas Valve C 42...
Page 187: ...APPENDIX D Falcon Alert Hold and Lockout Codes...
Page 188: ......
Page 208: ......
Page 210: ......
Page 231: ...Appendix E Falcon Lead Lag E 23 Figure 11 Falcon LL with EMS for remote enable remote setpoint...
Page 232: ...Falcon Lead Lag Appendix E E 24 Figure 12 Falcon Lead Lag with EMS for remote comms monitoring...
Page 245: ...Appendix E Falcon Lead Lag E 37 Model CFW ClearFire hydronic boiler...
Page 282: ......
Page 283: ...APPENDIX F Falcon Program Module...
Page 284: ......
Page 285: ...Appendix F Program Module F 3...
Page 286: ...Program Module Appendix F F 4...
Page 287: ...Appendix F Program Module F 5...
Page 288: ...Program Module Appendix F F 6...
Page 289: ......
Page 290: ...e mail info cleaverbrooks com Web Address http www cleaverbrooks com...