Pro Ox 5900-BT-AIR Installation & Startup Guide
Page 10
www.cleanwaterstore.com
Rev. 02-26-2020
Attach the Bypass
Make sure there is lubricant on all three sets of
O-rings and insert and screw bypass onto end
connectors (O-rings are already on valve, with
the Inlet Air Check Valve on the left, Inlet side).
Screw the Elbow fittings onto the end of the
bypass and attach to In and Out service pipe.
Note:
There is supposed to be some “play” in the whole assembly. No need to over-tighten.
Electrical Connections
P = Power – Use this connection
B = Optional (not used, powered in backwash step only)
S = Optional (not used, powered in regeneration step only)
Connect the power supply to the control valve connection P. This is the connection on the outside of
the valve, nearest the side or outer section of the valve. Plug into a wall outlet.
B and S connections are used to power optional external relays, pumps, or solenoid valves (not used for
most residential applications).
Install 9V Battery (not included)
DO NOT INSTALL BATTERY UNTIL AFTER INITIAL BACKWASH!
Connect 9V battery to battery cable under control panel. Battery cable and battery will sit under control
panel.
Control panel can be easily removed to access battery cable if needed, no tools are required.
During power failures the battery will maintain the time of day if the battery has power. The display is
turned off to conserve battery power during this time. If a power failure occurs while the system is
regenerating, the motor will advance to a shut-off position to prevent constant flow to drain.