Figure 10: Mounting an ONS 15454 ETSI Shelf in a Rack
Two people should install the shelf; however, one person can install it using the temporary set screws included.
The shelf should be empty for easier lifting. The front door can also be removed to lighten the shelf.
Mounting Multiple Nodes
Most standard (Telcordia GR-63-CORE, 23-inch [584.2 mm]) seven-foot (2,133 mm) racks can hold three
ONS 15454 ETSI shelves, two air ramps, and a fuse and alarm panel. The following figure shows a three-shelf
ONS 15454 ETSI bay assembly.
Cisco ONS 15454 Hardware Installation Guide
29
Installing the ONS 15454 M12 (ANSI and ETSI) Shelf
Mounting Multiple Nodes
Summary of Contents for ONS 15454
Page 2: ... 2019 Cisco Systems Inc All rights reserved ...
Page 16: ...Cisco ONS 15454 Hardware Installation Guide xvi Contents ...
Page 28: ...Cisco ONS 15454 Hardware Installation Guide xxviii Preface Preface ...
Page 36: ...Cisco ONS 15454 Hardware Installation Guide 6 Overview Cisco ONS 15454 M6 Shelf ...
Page 510: ...Cisco ONS 15454 Hardware Installation Guide 480 Hardware Specifications Dimensions ...