Figure 145: Moving Deep-Front Panel and Shelf in line
Step 4
Align the deep-front panel with the shelf by performing these sub-steps at the same time:
a) Align the right and left retention features of the deep-front panel with the right and left notches present
on the top of the shelf (see
Figure 145: Moving Deep-Front Panel and Shelf in line, on page 224
).
b) Align the deep-front panel pins present at the bottom of the panel with the shelf hinges (see the following
figure).
Figure 146: Aligning the Deep-Front Panel and Shelf
The following figure shows the deep-front panel aligned with the shelf.
Cisco ONS 15454 Hardware Installation Guide
224
Installing the ONS 15454 M2 Shelf
NTP-G343 Install the Deep-Front Panel of the ONS 15454 M2 Shelf
Summary of Contents for ONS 15454
Page 2: ... 2019 Cisco Systems Inc All rights reserved ...
Page 16: ...Cisco ONS 15454 Hardware Installation Guide xvi Contents ...
Page 28: ...Cisco ONS 15454 Hardware Installation Guide xxviii Preface Preface ...
Page 36: ...Cisco ONS 15454 Hardware Installation Guide 6 Overview Cisco ONS 15454 M6 Shelf ...
Page 510: ...Cisco ONS 15454 Hardware Installation Guide 480 Hardware Specifications Dimensions ...