DLP-G688 Upgrade the ONS 15454 Multishelf with MS-ISC Card Configuration
Use this task to upgrade the existing ONS 15454 multishelf configuration that
has the MS-ISC card installed, with the ONS 15454 M6 subtending shelves and
Cisco Catalyst 3950.
Purpose
• Two Cisco Catalyst 3560 switches must be installed in same rack as the node
controller shelf; refer to the Cisco Catalyst 3560 product documentation for
installation instructions.
• Cross-over (CAT-5) LAN cables (3, plus 2 for each subtending shelf)
Tools/Equipment
•
NTP-G15 Install the Common Control Cards
•
NTP-G313 Install and Configure the TNC, TNCE, TSC, or TSCE Card
Prerequisite Procedures
As needed
Required/As Needed
Onsite
Onsite/Remote
None
Security Level
Use TCC3 cards in ONS 15454 node controller while connecting it to the ONS 15454 M6 subtending shelves
and when there are more than 12 subtending shelves.
Note
The CTC in ONS 15454 M6 shelf view displays the three ports of the MS-ISC card, and EMS and circuit
ports present on the ECU.
Note
Procedure
Step 1
Disconnect the ONS 15454 subtending shelf from the EAPs:
a) Remove the cross-over (CAT 5) LAN cable (connecting the ONS 15454 subtending shelf) from the SSC8
port of the right EAP.
b) Remove the cross-over (CAT 5) LAN cable (connecting the ONS 15454 subtending shelf) from the SSC8
port of the left EAP.
Step 2
Connect the EAPs to the Catalyst 3560:
a) Using a cross-over (CAT-5) LAN cable:
•
• Plug one connector to the SSC8 port of the right EAP.
• Plug the other connector to Port 1 of the active Catalyst 3560.
b) Using a cross-over (CAT-5) LAN cable:
•
• Plug one connector to the SSC8 port of the left EAP.
• Plug the other connector to Port 1 of the standby Catalyst 3560.
Installing the ONS 15454 M6 Shelf
153
Installing the ONS 15454 M6 Shelf
DLP-G688 Upgrade the ONS 15454 Multishelf with MS-ISC Card Configuration