PART
QTY
A 3-WAY CORNERS
4
B 4-WAY CORNERS
6
C 16” PIPE
W/REDUCED END
5
F
64” PIPE W/
REDUCED END
8
H
NET HANGERS
37
I
PIPE END CAPS
10
J
SELF-DRILLING SCREWS
13
10' LENGTHS OF EMT
23
You will need an area about 61' long and 17
'
6”
wide.
It is recommended that you mark off this area before starting
Nut setter included
CONSTRUCTING YOUR FRAME
1
Lay out two of the 3-way corners (A) 12' apart at one end, where your frame will be, with the
4” corner piece facing toward the other end of the frame.
2
Measure 60' from the first 3-way corners (A) to the other end of the frame and lay out the other
two 3-way corners (A) with the 4” corner piece facing the other end of the frame.
3
Lay out the 4-way arch corners (B) between the end 3-way corners (A) so that they are
about 15' apart.
4
Assemble the five arch tops by attaching one 10' length of EMT to one 16” pipe (C).
Insert a self-drilling screw (
J
) at the joints.
5
10 of the 10' lengths of EMT are your arch legs.
6
Complete assembling the arches by attaching the legs to each of the arch corners. Attach
the end caps (
I
) to the bottom of the legs.
7
Assemble the eight runners, that go between the arches, by attaching a 64” pipe (
F)
, to a 10'
length of EMT. Insert a self-drilling screw
(J)
at all joints.
8
Stand up one end arch and attach a 15' runner to each of the end corners. Stand up the second
arch and attach the runners to it. Proceed to stand up the remaining arches and connect all
the
runners. Tighten the corner bolts. Your frame should end up being a little over 60'.
HANGING YOUR BATTING CAGE
1
Attach the net hangers (
H
) to the runners of the frame, about four feet apart, by laying the rope
end
over
the pipe and inserting the carabiner end through the loop. Then attach a net hanger (
H
) to the
middle of
arch
.
2
Lay out your batting cage inside the frame and find the three ropes on top of the cage at one end,
and attach to the top of the end arch. Proceed to attach the net hanger carabiners, on one side of
the frame to the top ropes on same side of the batting cage. Attach the net hanger carabiner in the
middle of the arches to the middle rope on the batting cage. Then attach the remaining carabiners
to the batting cage on the remaining side. Make necessary adjustments.
3
Tie the other end ropes of the batting cage to the top of the other end frame.
4
Tie the four rope tails on the batting cage to the bottom of the end arches to prevent the wind
from blowing the net inward.
To secure the frame, we recommend that you attach two 18' ropes to each end of the
frame and stake the ropes to the ground. Ropes and stakes are not included.
CM-602024TPC
F1.5
The following parts are included for your frame. Please review the parts you received with your batting
cage and frame to be sure you have all the parts listed.
1 of 2
Instructions for the
Cimarron 60
'
x12
'
x10
'
Complete
Batting Cage Frame
0
706
17 sjh