NOTES
1.

Motor, Solenoid Valve and Dotted Control Wiring are included if
Motor and Pump package is supplied. Solenoid Valve only is sup-
plied with 99117 Water feed.

2.

1/3 HP Motor is controlled directly without use of Motor Starter.

After proper wiring and piping of boiler system is complete, testing of
controls can start. 

Before testing controls, it is recommended that all

contactor fusing be removed.

This is to prevent possible element fail-

ure under test conditions.

CAUTION:

Be sure all electrical connections are tight

before energizing boiler. Reset all manual reset con-
trols by pushing reset buttons on: (1) high limit control
located on top of boiler and (2) McDonnell-Miller locat-
ed on side of boiler.

A. McDONNELL & MILLER LOW WATER CUTOFF CON-

TROL OPERATION AND TESTING

1.

Be sure all valves from incoming water supply are fully open. Turn
boiler switch to “ON” position, pump or solenoid valve will ener-
gize, allowing boiler to fill with water. Proper water level is auto-
matically reached with level control supplied. Pump or solenoid
feed will shut off at proper water level. Contactor(s) will energize,
supplying power voltage to elements.

2.

Checking operation of pump switch. (Figure 11) With water level
visible in sight glass, partially open drain valve at bottom of boil-
er. If automatic blowdown supplied, push manual blowdown
switch until valve open light is on, hold for few seconds. Water
level will fall, allowing float to trip pump switch to “ON” position.
Close drain valve or release manual blowdown switch. Pump
motor or solenoid valve will energize and water level will resume
to normal level in sight glass.

3.

Checking low water cutout switch operation, open drain valve
completely. If automatic blowdown supplied, push in and hold
manual blowdown switch until water level falls enough to trip
cutout switch. Close drain valve or release manual blowdown
switch. If low water cutout is automatic reset, pump or solenoid
will return water level to normal. If low water cutout is manual
reset, then manual reset button on McDonnell & Miller low water
cutoff control must be pushed to complete circuit. 

Turn off boiler.

Reinstall contactor fuses.

B. ADJUSTING OPERATING PRESSURE CONTROLS
1.

Chromalox boilers are supplied with operating and high limit pres-
sure controls. One is used for controlling the operating pressure of
the boiler while the other is used as a high limit control. To deter-
mine the difference in the controls, the high limit has a manual
reset lever on top of the case. Also, there is no differential scale
present.

2.

On all controls, the pressure adjusting screw on the top of the case
sets the desired pressure. Turning the screw counterclockwise
reduces the pressure setting (see Figure 12). High limit control
should be set at 10 psig above the operating pressure of the boiler.

3.

The differential adjusting screw on the operating control is set in
the same manner as the pressure adjusting screw. This scale set-
ting, plus the main scale setting, equals cutout pressure of the oper-
ating control. (Scale A thru F equals 3 psi per letter. L9l B only)
L404A Differential is indicated on Scale Plate.

To check operation of the controls, close steam outlet valve and
adjust operating pressure control to a 

low pressure setting

. Also,

set high limit control at 10 psig above operating pressure control.

Turn on boiler

and allow pressure to build up. When pressure

gauge reading approaches set point of pressure control, the switch
will trip and shut off boiler. 

Turn boiler main switch to “OFF".

To reset pressure control, bleed off enough pressure in the boiler
by opening steam outlet drain, or blowdown valve to allow the
operating control to reset.

4. HIGH LIMlT PRESSURE CONTROL OPERATION.

The

high limit is tested in the same manner but with the operating con-
trol set above the pressure setting of the high limit. (Figure 13)

CAUTION: THIS IS FOR TEST PURPOSES ONLY!

When the high limit trips turn off boiler and reset high limit to
proper setting, the manual reset level must be pushed to resume
operation upon startup.

5

PRE-OPERATION CHECK

Pump

Line

Low Water
Cut-Off
Terminals

Alarm
Circuit
Terminals

Cut-Off and

Alarm Switch

Adjusting
Screws

Pump

Switch

Pump

Circuit

Terminals

Figure 11 – Automatic Reset Low Water Cutoff Junction Box

Pump

Line

For pump motors 1/2 h.p. Single Phase
or less, or D.C. 1/4 h.p. or less,
wire as main line switch.

Wiring Diagram – McDonnell & Miller Low Water Cutoff and Pump Control

Differential
Adjusting
Screw

Pressure
Adjusting
Screw

Mercury

Switch

Differential
Setting
Indicator

Pressure
Setting
Indicator

Operating Lever

Diaphragm Assembly

Leveling
Indicator Pointer

Index Mark

Figure 12 –  Pressure Control

Pressure
Adjusting
Screw

Manual

Reset
Lever

Mercury

Switch

Index

Mark

Pointer

Leveling

Indicator

Diaphragm

Assembly

Operating Lever

Pressure

Setting

Indicator

Scaleplate

Wiring Diagram – McDonnell & Miller Low Water Cutoff and Pump Control

Summary of Contents for CHS-1080

Page 1: ...t Boilers INSTALLATION CAUTION To avoid electrical shock hazard boilers must be suitably grounded to earth NOTE Chromalox boilers are pre tested before shipment no internal piping or wiring is necessa...

Page 2: ...34 40 2 NPT 1 NPT 1 NPT CHS 720 thru CHS 810 76 58 45 47 94 6 1 1 2 38 44 2 NPT 1 NPT 1 NPT CHS 945 thru CHS 1080 76 68 45 47 94 6 1 1 2 38 44 2 NPT 1 NPT 1 NPT CHS 1215 thru CHS 1620 86 76 56 50 98...

Page 3: ...ety feature that prevents a dangerous situ ation should a contactor or relay stick Activation of the shunt trip device will completely disconnect the boiler from the power sup ply See Figure 7 3 Since...

Page 4: ...Groups To Other Heater Groups Typical 3 Phase Heater Group To Power Curcuit Relay Step Sequencer Figure 9 Power Circuit Detail Low Water Probe 120 Volt Control Voltage Hi Limit Control Electronic Resi...

Page 5: ...he other is used as a high limit control To deter mine the difference in the controls the high limit has a manual reset lever on top of the case Also there is no differential scale present 2 On all co...

Page 6: ...sure Do not push reset until boiler has filled with water The use of chemical boiler cleaning compounds in these boilers voids all warranties unless approved by manufacturer Some compounds will damage...

Page 7: ...ated on the inside of the control panel to boiler normal if the boiler is to be shut down each night Set it to 24 hour duty if the boiler is to remain on continuously 24 hours per day except during bl...

Page 8: ...of the controlled medium will cause a change in the number of elements energized to compensate for it thus keeping the pressure constant This process is called modula tion PROPORTIONAL PRESSURE CONTR...

Page 9: ...boiler off remove wiring from pressure control on sequencer low voltage terminal board 2 Turn on boiler to supply the voltage to sequencer Short terminal R and B for counter clockwise rotation and ter...

Page 10: ...gized for safety When power resumes the control will re stage the loads one at a time Refer to the diagram for visual description of progressive sequencing PROGRESSIVE SEQUENCING The solid state seque...

Page 11: ...nge 5 Thoroughly clean boiler flange of all foreign material Be certain no part of old gasket remains on boiler flange 6 Apply Slic Tite Gasket Compound or equal to both surfaces of new gasket supplie...

Page 12: ...amp 128 118530 003 Power Circuit Fuse Class J 100 amp 128 118530 004 Valves and Gauges Description Part Number Pressure Gauge 3 1 2 160 344 118529 024 Gauge Glass Assembly 347 118537 002 Sight Glass 3...