Typical Plumbing Installation of a Steam Boiler with Condensate Return System

CES — Dimensions (In.)

DIMENSIONS

INSTALLATION

Model

A

B*

C

D

E

F

G

H

I

J

K

L

CES-6

37 22-1/2 30 15-1/4 20 30-1/2 9-1/2

16

1/2

1

1/2

1/2

CES-9

37 22-1/2 30 15-1/4 20 30-1/2 9-1/2

16

1/2

1

1/2

1/2

CES-12

37 22-1/2 30 15-1/4 20 30-1/2 9-1/2

16

1/2

1

1/2

1/2

CES-18

37 22-1/2 30 15-1/4 20 30-1/2 9-1/2

16

1/2

1

1/2

1/2

CES-24

43-1/2 26

46 17-1/2 23 34-1/2 16-1/2 24-1/2

1

1

1

3/4

CES-30

43-1/2 26

46 17-1/2 23 34-1/2 16-1/2 24-1/2

1

1

1

3/4

CES-36

43-1/2 26

46 17-1/2 23 34-1/2 16-1/2 24-1/2

1

1

1

3/4

CES — Dimensions (In.)

Model

A

B*

C

D

E

F

G

H

I

J

K

L

CES-48

43-1/2 26

46 17-1/2 23 34-1/2 16-1/2 24-1/2

1

1

1

3/4

CES-60

43-1/2 26

46 17-1/2 23 34-1/2 16-1/2 24-1/2

1

1

1

3/4

CES-72

43-1/2 26

46 17-1/2 23 34-1/2 16-1/2 24-1/2

1

1

1

3/4

CES-100

63-1/2 30

55

21

27

36 16-3/4 37-1/2 1-1/2 1-1/4

1

3/4

CES-135

63-1/2 32

55 20-1/2 26 37-1/2 16 37-1/2

2

1-1/4

1

3/4

CES-160

63-1/2 32

55 20-1/2 26 37-1/2 16 37-1/2

2

1-1/4

1

3/4

CES-180

63-1/2 32

55 20-1/2 26 37-1/2 16 37-1/2

2

1-1/4

1

3/4

Note:

When installing boiler, allow sufficient room (21” minimum) to

facilitate removal of elements if and when necessary.

1.

The boiler should be mounted  on a solid level foundation.

2.

WARNING:

A minimum distance of 18” between

boiler and any combustible material must be main-
tained.

3.

Complete all piping to boiler. Connect water line to tagged fitting
on the motor and pump assembly, if used, or to tagged fitting on
water control feeder.

4.

When any type of feed other than a pump feed is used — the exist-
ing water supply must be 10 pounds greater than the boiler operat-
ing pressure to assure water supply maintains proper water level in
boiler. Otherwise, lack of water can cause heater failure. Keep feed
water line valves open at all times except during blowdown.

5.

All water feed systems are connected to water inlet check valve.

6.

Connect steam line (with Globe valve) to boiler steam outlet.
Valve should be placed as close as possible to boiler outlet and
sized per label on boiler.

7.

To insure maximum efficiency of supplied kW, all piping from
outlet should be insulated.

8.

Drain and relief valve piping should be in accordance with state
and local codes. Floor drain to be provided directly below unit.

9.

All electrical wiring should be done by licensed electrician in
accordance with national and local electrical codes.

10.

If pump is located less than 30 feet from boiler, a second
check valve is required.

Vacuum

Breaker

Safety

Valve

Drain

Boiler

Check

Valve

Check

Valve

Check

Valve

Globe

Valve

Gate

Valve

Heat

Exchanger

Water/Steam

Separator

Insulated Steam Lines

(Pitch Down 5˚)

Pitch Down 5˚

Vent

Condensate

Return

Drain

Gate

Valve

Strainer

Return

Cold Water

Make-Up

Centrifugal

Turbine Pump

Steam

Water

Condensate

Vapor

(Typical

Load)

Trap

Trap

3

*Add two inches for transformer.

Summary of Contents for CES-100

Page 1: ...3 50 6 17 CES 135 13 9 136 30 5 410 8 50 4 50 8 17 1 30 CES 160 16 1 157 5 30 5 475 7 60 3 60 7 22 5 CES 180 18 4 180 30 5 543 8 60 4 60 8 22 5 Chromalox DIVISION 4 SECTION CES SALES REFERENCE DATE SE...

Page 2: ...nection Conduit Box Element I Steam Outlet Sight Glass Element Access Door 5 8 7 16 Bolt Hole typical Drain Blowdown Valve K A B C Check Valve D H F E G Operating Pressure Control Safety Valve Outlet...

Page 3: ...ust be main tained 3 Complete all piping to boiler Connect water line to tagged fitting on the motor and pump assembly if used or to tagged fitting on water control feeder 4 When any type of feed othe...

Page 4: ...ed 6 WARNING Substitution of components or modifica tion of wiring system voids the warranty and may lead to dangerous operating conditions 7 SPECIAL INSTRUCTIONS FOR CUSTOMERS SUPPLY ING THEIR OWN CO...

Page 5: ...R C2 FU4 FU5 FU6 2L1 2L3 2L2 Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 3 2PS BR Heater Contactor Feed Water Boiler On 3 GND B FU6 B 1PB Off 1 GND 1 HTR C...

Page 6: ...3 C2 FU7 FU8 FU9 C3 3L1 1L3 3L2 3 HTR C3 Heater Contactor Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 5 2PS BR Heater Contactors Feed Water Boiler On 3 GND...

Page 7: ...C3 C4 FU 10 11 12 4 Htr FU10 FU11 FU12 C4 4L1 4L3 4L2 4 HTR C4 Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 7 2PS BR Heater Contactor Feed Water Boiler On...

Page 8: ...ND Cabinet Exterior Left Side Cabinet Exterior Right Side Panel Layout Feed Water Electrical Connection Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 9 FU 1...

Page 9: ...H1 H4 H2 H3 FU24 FU23 FU22 FU21 FU20 FU13 C8 C7 7 HTR 6 HTR 7L1 8L3 8L2 8L1 5L3 7L2 C5 C7 Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 11 FU 1 2 3 FU 4 5 6...

Page 10: ...7L2 FU FU FU C7 C6 Heater Contactor Heater Contactor Heater Contactor Heater Contactor Heater Contactor Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 13 FU...

Page 11: ...in valve or release man ual blowdown switch If low water cutout is automatic reset pump or solenoid will return water level to normal If low water cutout is manual reset then manual reset button on Mc...

Page 12: ...ustomer Supplied 2 Turn on boiler and allow pressure to build up to operating pressure 3 Only open globe valve at quarter turns at first introducing smaller amounts of steam into process Avoid opening...

Page 13: ...E CLOSED and the BOILER ON should light up again Now turn the wheel on the large timer until the OFF tab passes the TIME NOW arrow The BOILER ON light should go out and the valve should begin to open...

Page 14: ...circuit balance is achieved The slightest change in the pressure of the controlled medium will cause a change in the number of elements energized to compensate for it thus keeping the pressure constan...

Page 15: ...stage loads of the type used in Chromalox steam boilers It features progressive sequencing first on first off which equalizes the operating time of each load This control gives visual indication of e...

Page 16: ...ed 3 Connect piping from discharge to water inlet check valve on boil er with minimum of 90 bends or other restrictions 4 All electrical wiring should be done by licensed electricians in accordance wi...

Page 17: ...sure to drop to zero before ser vicing WARNING Provision should be made to prevent water damage from any eventual leaking of boiler or com ponents Install near a floor drain 2 On automatic feed units...

Page 18: ...end life 2 If generator is undersized for its application heaters will be over worked and reach end of life sooner 3 Element has been overheated due to excessive scale build up The scale acts as an i...

Page 19: ...50Hz 193 300175 002 Motor only used in ES 38020 115V 60Hz 193 300175 004 Strainer used in ES 38020 351 118664 001 V Band Mount used in ES 38002 ES 38020 355 300174 001 Solenoid Valve used in ES 38002...

Page 20: ...0 amp 600V 128 121133 066 60 amp 600V 128 121133 067 Fuse Block 35 60 amp 60 amp 600V 129 047445 002 Power Terminal Blocks 3 pole 115 amp 1 line circuit 1 load circuits 303 071809 032 3 pole 175 amp 1...

Reviews: