OPTIONAL EQUIPMENT FOR STEAM BOILERS

IF A CONTROLLER SEEMS TO OPERATE IMPROPERLY

If the controller is suspected of operating improperly, it may be

further checked as follows:

1.

Leave the controller installed where it is, but disconnect all power
to the boiler.

2.

Loosen the cover screw below the main scaleplate and remove the
cover.

3.

Disconnect the wires from the controller.

4.

Connect an ohmmeter between controller terminals B and W to
measure the resistance of the potentiometer in the controller. The
ohmmeter should read about 135 ohms on an L91B.

5.

Connect the ohmmeter between controller terminals W and R and
raise the set point of the controller above the actual pressure being
measured. The ohmmeter should read the full value of the poten-
tiometer measured in step 4 (135 ohms for an L91B).

6.

Slowly lower the set point of the controller while observing the
ohmmeter reading. The resistance should drop to zero at some set
point below the actual pressure.

7.

An approximation of the proportioning range can be made by
observing the change in set point required for a resistance change
from zero to full value.

8.

When the controller is operating properly, reconnect the wires,
replace the cover, tighten the cover screw, and reset the controller
to the desired value.

9.

Reconnect power to the controlled motor.

BOILER SEQUENCE — SOLID STATE
Solid State Progressive Sequencer

The solid state progressive sequencer provides accurate elec-

tronic control of multi-stage loads of the type used in Chromalox
steam boilers. It features progressive sequencing (first on-first off)
which equalizes the operating time of each load. This control gives
visual indication of each energized stage by means of integral
solid state light emitting diodes. In the event of power interrup-
tion, all heating elements are immediately de-energized for safety.
When power resumes, the control will restage the loads one at a
time.

The solid state sequencer operates on 120V AC/60 Hz and

each output is relay switched with a load rating of 125 VA at 120V
AC.

The input to the sequencer is a 0-135 OHM potentiometer sup-

plied on the operating pressure control. The sequencer has a sen-
sitivity control which is adjustable from min. to max. This sensi-
tivity control defines the amount of resistance (pressure) deviation
allowed before adding or subtracting a load. Potentiometer resis-
tance should decrease with increasing pressure. Connections are
made to red and white terminals of proportional pressure control.
See Wiring Diagram 337-300164-452 for Boiler With Solid State
Sequencer.

Main Scale

Adjusting

Screw

Proportioning Range

Adjusting Screw

R

W

B

Main Scale

Setting

Indicator

Set Point

Increase

R

W

B

Ohmmeter

Increases to

135 Ohms

Terminals are not Labeled, but Screw-Heads are

Color Coded Red (R), White (W) and Blue (B).

15

Pressure

Control

5 Step

Control

Sequencer

Auto

Blowdown

System

Heater Contactor

Heater Contactor

Heater Contactor

Heater Contactor

Feed Water
Solenoid Valve

Boiler
On

Optional Transformer

480/120V

480V 3Ø 60 HZ

Typical wiring for boilers equipped with Auto Blowdown System and/or

Solid State Sequencer.

Solid State Sequencer

Summary of Contents for CES-100

Page 1: ...3 50 6 17 CES 135 13 9 136 30 5 410 8 50 4 50 8 17 1 30 CES 160 16 1 157 5 30 5 475 7 60 3 60 7 22 5 CES 180 18 4 180 30 5 543 8 60 4 60 8 22 5 Chromalox DIVISION 4 SECTION CES SALES REFERENCE DATE SE...

Page 2: ...nection Conduit Box Element I Steam Outlet Sight Glass Element Access Door 5 8 7 16 Bolt Hole typical Drain Blowdown Valve K A B C Check Valve D H F E G Operating Pressure Control Safety Valve Outlet...

Page 3: ...ust be main tained 3 Complete all piping to boiler Connect water line to tagged fitting on the motor and pump assembly if used or to tagged fitting on water control feeder 4 When any type of feed othe...

Page 4: ...ed 6 WARNING Substitution of components or modifica tion of wiring system voids the warranty and may lead to dangerous operating conditions 7 SPECIAL INSTRUCTIONS FOR CUSTOMERS SUPPLY ING THEIR OWN CO...

Page 5: ...R C2 FU4 FU5 FU6 2L1 2L3 2L2 Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 3 2PS BR Heater Contactor Feed Water Boiler On 3 GND B FU6 B 1PB Off 1 GND 1 HTR C...

Page 6: ...3 C2 FU7 FU8 FU9 C3 3L1 1L3 3L2 3 HTR C3 Heater Contactor Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 5 2PS BR Heater Contactors Feed Water Boiler On 3 GND...

Page 7: ...C3 C4 FU 10 11 12 4 Htr FU10 FU11 FU12 C4 4L1 4L3 4L2 4 HTR C4 Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 7 2PS BR Heater Contactor Feed Water Boiler On...

Page 8: ...ND Cabinet Exterior Left Side Cabinet Exterior Right Side Panel Layout Feed Water Electrical Connection Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 9 FU 1...

Page 9: ...H1 H4 H2 H3 FU24 FU23 FU22 FU21 FU20 FU13 C8 C7 7 HTR 6 HTR 7L1 8L3 8L2 8L1 5L3 7L2 C5 C7 Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 11 FU 1 2 3 FU 4 5 6...

Page 10: ...7L2 FU FU FU C7 C6 Heater Contactor Heater Contactor Heater Contactor Heater Contactor Heater Contactor Wire Color Code B Black BR Brown R Red O Orange Y Yellow G Green BL Blue W White Diagram 13 FU...

Page 11: ...in valve or release man ual blowdown switch If low water cutout is automatic reset pump or solenoid will return water level to normal If low water cutout is manual reset then manual reset button on Mc...

Page 12: ...ustomer Supplied 2 Turn on boiler and allow pressure to build up to operating pressure 3 Only open globe valve at quarter turns at first introducing smaller amounts of steam into process Avoid opening...

Page 13: ...E CLOSED and the BOILER ON should light up again Now turn the wheel on the large timer until the OFF tab passes the TIME NOW arrow The BOILER ON light should go out and the valve should begin to open...

Page 14: ...circuit balance is achieved The slightest change in the pressure of the controlled medium will cause a change in the number of elements energized to compensate for it thus keeping the pressure constan...

Page 15: ...stage loads of the type used in Chromalox steam boilers It features progressive sequencing first on first off which equalizes the operating time of each load This control gives visual indication of e...

Page 16: ...ed 3 Connect piping from discharge to water inlet check valve on boil er with minimum of 90 bends or other restrictions 4 All electrical wiring should be done by licensed electricians in accordance wi...

Page 17: ...sure to drop to zero before ser vicing WARNING Provision should be made to prevent water damage from any eventual leaking of boiler or com ponents Install near a floor drain 2 On automatic feed units...

Page 18: ...end life 2 If generator is undersized for its application heaters will be over worked and reach end of life sooner 3 Element has been overheated due to excessive scale build up The scale acts as an i...

Page 19: ...50Hz 193 300175 002 Motor only used in ES 38020 115V 60Hz 193 300175 004 Strainer used in ES 38020 351 118664 001 V Band Mount used in ES 38002 ES 38020 355 300174 001 Solenoid Valve used in ES 38002...

Page 20: ...0 amp 600V 128 121133 066 60 amp 600V 128 121133 067 Fuse Block 35 60 amp 60 amp 600V 129 047445 002 Power Terminal Blocks 3 pole 115 amp 1 line circuit 1 load circuits 303 071809 032 3 pole 175 amp 1...

Reviews: