6.2 CONNECT THE INLET AND
THE OUTLET TO THE TUNNEL
• At first remove the squared metal plates in every
corner of the tunnel (4 total). The belt conveyor is
on moving railings, these plates are firmly screwed
to avoid accidental moving of the belt conveyor
lifting system.
• Do not dispose the plates. After the inlet and the
outlet have been connected, these plates will be
eventually screwed in the same position again.
CONNECT THE INLET
• Identify the inlet by the label, usually it's longer
and heavier than the oulet.
• To lift the inlet in position secure it to a suitable
forklift with anchor straps in the corners.
Alternatively 3 or more Operators are needed to
manually lift the structure.
• Align the inlet to the plates of the tunnel as shown
in the picture.
• Insert 6 screws from the inside to attach the
plates for each side. Do not tight completely yet in
order to suspend the structure and be able to level
it.
• 2 or more operators are needed to level the
structure, one adjust the height and tilt of the inlet
while the other tigthen the screws to fix it in
position, refer to the picture. Measure the level on
both sides and on the roller of the belt.