4.3 Commissioning Steps
Complete the checklist above before commissioning the inverter as follows:
1.)
Turn on the AC circuit breaker.
2.)
Turn on the DC circuit breaker. (Skip these two steps if there are no
circuit breakers.)
3.)
Switch the DC Switch to the “ON” position. When the energy
supplied by the PV array is sufficient, the LED of inverter will light up.
The inverter will then start up.
4.4
Connection to the inverter – Wireless
Once powered, the inverter will automatically create a wireless network
that will be visible as an Access Point from the user devices (tablet,
smartphone, etc.), connection to the inverter via Wi-Fi .
1.)
Open the CPS Connect Pro app and select
No-LCD Inverter
.
2.)
Enable the wireless connection on the device which is being used for
the board setup (tablet or smartphone) and connect it to the Access
Point created by the inverter system: the name of the wireless
network created by the system that the connection should be
established with, will be: CPLK-XXXXXXX where “X” can be found
on the “LinKIT Label” placed on the side of the WiFi module.
3.)
Please input the password
“
Password
”
(Capital P)
4.)
Touch the
Setting
icon and input the password “1111” to access the
Settings interface.
5.)
Select the Inverter Parameters tab to set the Grid Code, PV Link
Type, Neutral Line, RS485 and Inverter Clock” as shown in Figure 4-
1.
Summary of Contents for CPS SCH Series
Page 2: ......
Page 4: ......
Page 43: ...39 Figure 3 25 AC Output Cable Connection Distributed Wire box L1 L2 L3 ...
Page 45: ...41 Figure 3 27 AC Output Cable Connection Centralized Wire box Ver 2 ...
Page 58: ...54 Figure 4 1 System setting ...
Page 81: ...77 5 4 2 6 Others The REF column is reference to Table 5 7 Enable functions ...