move across the rack at the bottom of the toprail. At the top of the lift’s
travel, pull down the toprail safety latch banjo until the Reset locks it open.
Adjust and plumb cross rails and legs as necessary. When you are positive
the lift is moving freely, you may finally drill and install the anchor bolts in
the offside legs.
28. The next phase is to locate and install the tracks, ramps and stops on the
lube rack lift. See Track, Ramp & Stop Assy. drawing. Step #1 is make
sure the tracks are centered on the cross rails and are 36” apart on the holes
where the bridge mounts. See Fig. #13. Secure track using ½” U-bolts.
29. Step #2 is to bolt the Bridge Weldm’t. to the tracks using the 5/16-
18UNC x 1” bolts and 5/16 lock washers. See Fig. #14.
30. Step #3 & #4 is to raise the lift about 30” and bolt the Long and Short
Walkway on the tracks using the 1/2-13UNC x 1¼” bolts, ½ flat washers
and ½ lock washer as shown in Fig. #14.
31. Step #5 is to bolt the ladder on the short walkway as shown in Fig. #14
using the ½-13UNC x 1¼” bolt, flat washer & nylon lock nut.
32. Step #6, #7 & #8 is to bolt the long, short and ladder handrail to the
walkways and ladder as shown in Fig. #15. Use the 3/8-16UNC x 1 ¼”
bolts, 3/8 flat washers and 3/8 lock washers.
33. Step #9 and #10 is to bolt the gatepost and hinge the LH/RH gates as
shown in Fig. #15. Use the 3/8-16UNC x ¾” bolts and 3/8 lock washers.
34. Now that the lift is fully assembled, cycle the lift to it’s maximum
height and back to the ground at least 3 full cycles without any load to
remove air from the hydraulic system.
SAFETY AND OPERATING PROCEDURES
Before attempting to operate this lift, be familiar with it is basic operational
and safety procedures.
1. Prior to lifting a vehicle, walk around the lift and check for any
9