chain to each crossrail connector using 5/16 x 3 1/2” Shoulder bolt and nuts.
Do not substitute this bolt!!!!
Repeat on other crossrail. Replace fitting on
cylinder.
21. Attach the power unit at its location on the mainside leg with supplied
hardware.
22. Before connecting the hydraulic hoses from the power unit to the
cylinder you must first install two 90 deg. fittings (2501-06-06) on the
cylinder and two 90 deg. fittings with o-rings (6801-LL-06-06) on the power
unit. Now the pressure and return hoses can be attached. The 108” pressure
hose (ALIF-412-029) goes from the fitting on the cylinder next to the rod to
the fitting of the power unit on the side of the handle (pressure port). The
48” return hose (ALIF-412-030) goes from the fitting of the cylinder next to
the power unit to the fitting of the power unit on the opposite side of the
handle (return port).
23. Have electricity hooked up to the power unit -220 single phase. We
recommend a 30 amp breaker and a 30 amp twist lock plug be installed near
the power unit.
24. Remove breather cap from power unit. Place a funnel into hold. Fill
reservoir with 14 qts of non-detergent 10 wt. hydraulic fluid or ATF
transmission fluid. Install breather cap.
OFFSIDE LEGS ARE NOT ANCHORED YET.
25. Position tracks on the cross rails. Raise the lift up about 12”. Place a
level on the crossrail and level the crossrail by adjusting the nut on the
crossrail connector.
26. After leveling cross rails, adjust and plumb the offside legs so that the
cross rail chains in the offside legs hang straight. Use a level. Cycle the lift
all the way up and down making sure that each corner is running freely. The
offside legs may vary from the chalk line slightly. It is more important that
the legs are square and plumb, and that the lift moves up and down freely.
27. Raise the lift to the top of its travel. Check the positioning of the cross
rails in the legs as the lift is raised. The single point toprail safety latch will
8