Fig. 46 — Typical Smoke Detector Wiring
Sensor and Controller Tests
See Table 11.
SENSOR ALARM TEST
The sensor alarm test checks a sensor’s ability to signal an
alarm state. This test requires the use of a field-provided SD-
MAG test magnet.
Sensor Alarm Test Procedure
1. Hold the test magnet where indicated on the side of the
sensor housing for seven seconds.
2. Verify that the sensor’s Alarm Light Emitting Diode
(LED) turns on.
3. Reset the sensor by holding the test magnet against the
sensor housing for two seconds.
4. Verify that the sensor’s Alarm LED turns off.
CONTROLLER ALARM TEST
The controller alarm test checks the controller’s ability to initi-
ate and indicate an alarm state.
Controller Alarm Test Procedure
1. Press the controller’s test/reset switch for seven seconds.
2. Verify that the controller’s Alarm LED turns on.
3. Reset the sensor by pressing the test/reset switch for two
seconds.
4. Verify that the controller’s Alarm LED turns off.
DIRTY CONTROLLER TEST
The dirty controller test checks the controller’s ability to initi-
ate a dirty sensor test and indicate its results.
Dirty Controller Test Procedure
1. Press the controller’s test/reset switch for two seconds.
2. Verify that the controller’s Trouble LED flashes.
A
E
F
C
D
B
IMPORTANT:
OPERATIONAL TEST ALERT
Failure to follow this ALERT can result in an unnecessary
evacuation of the facility.
This test places the duct detector into the alarm state. Unless it is
part of the test, disconnect all auxiliary equipment from the
controller before performing the test. If the duct detector is
connected to a fire alarm system, notify the proper authorities
before performing the test.
IMPORTANT:
OPERATIONAL TEST ALERT
Failure to follow this ALERT can result in an unnecessary
evacuation of the facility.
This test places the duct detector into the alarm state. Unless it is
part of the test, disconnect all auxiliary equipment from the
controller before performing the test. If the duct detector is
connected to a fire alarm system, notify the proper authorities
before performing the test.
IMPORTANT:
OPERATIONAL TEST ALERT
Failure to follow this ALERT can result in an unnecessary
evacuation of the facility.
Pressing the controller’s test/reset switch for longer than seven
seconds will put the duct detector into the alarm state and
activate all automatic alarm responses.
Summary of Contents for WeatherMaker 50KCQ A04 Series
Page 34: ...34 Fig 53 RTU Open Overlay for Economizer Wiring ...
Page 35: ...35 Fig 54 VFD Overlay for W2770 Controller Wiring ...
Page 70: ...70 Fig C 50KCQ A04 A05 A06 Control Wiring Diagram 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Page 71: ...71 Fig D 50KCQ A04 A05 A06 Power Wiring Diagram 208 230 1 60 APPENDIX D WIRING DIAGRAMS ...
Page 72: ...72 Fig E 50KCQ A04 A05 A06 Power Wiring Diagram 208 230 3 60 APPENDIX D WIRING DIAGRAMS ...
Page 73: ...73 Fig F 50KCQ A04 A05 A06 Power Wiring Diagram 460 3 60 APPENDIX D WIRING DIAGRAMS ...
Page 74: ...74 Fig G 50KCQ A04 A05 A06 Power Wiring Diagram 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Page 75: ...75 Fig H 50KCQ Premier Link Control Diagram APPENDIX D WIRING DIAGRAMS ...
Page 76: ...76 Fig I 50KCQ RTU Open Control Diagram APPENDIX D WIRING DIAGRAMS ...