Fig. 61 — Disassembly and Assembly of EXV Motor
Table 41 — Color Indicators When Moisture Is Present in Refrigerant
Liquid Line Service Valve
This valve is located immediately ahead of filter drier, and has a
1
/
4
-in. access connection for field charging. In combination with
compressor discharge service valve, each circuit can be pumped
down into the high side for servicing with plate fin coils. Micro-
channel Heat Exchanger (MCHX) coils have much smaller vol-
ume and cannot accommodate the entire circuit charge.
Compressor Assembly
The 30XV units utilize Greenspeed Intelligence for efficient
operation. The compressor is controlled by a VFD. See Fig. 62
for a view of a typical 06Z compressor. For optimal efficiency
the compressor uses a VI valve to change the inlet area of the
lobes at different loading points. The valve is opened or closed
by a solenoid on the compressor. The control logic looks at cal-
culated parameters to determine the switch point of the valve.
VI VALVE TROUBLESHOOTING
Use the quick test table (
Main Menu
Quick Test Table
Circuit X VI
) to enable the VI valve output. Enable the valve
output and verify the coil solenoid is energized.
SUCTION VICTAULIC COUPLING INSTALLATION
1. The outside surface of the pipe, between the groove and
the pipe end, must be smooth and free from indentations,
projections (including weld seams), and roll marks to en-
sure a leak-tight seal. All oil, grease, loose paint, and dirt
must be removed. The Victaulic gasket used for refriger-
ant system piping will have a yellow mark on one side of
the gasket lips.
2. Apply a thin coat of Victaulic lubricant or silicone lubricant
to the gasket sealing lips and exterior.
3.
4. Position the gasket over the pipe end. Make sure the gasket
does not overhang the pipe end.
5. Align and bring the two pipe ends together. Slide the gasket
into position and center it between the grooves in each pipe
end. Make sure no portion of the gasket extends into the
groove in either pipe end.
6. Install the housings over the gasket. Make sure the housings’
keys engage the grooves completely on both pipe ends.
COLOR INDICATOR
R-134a, 75°F (24°C) (ppm)
R-134a, 125°F (52°C) (ppm)
Green — Dry
< 30
< 45
Yellow-green — Caution
30-100
45-170
Yellow — Wet
>100
>170
CLO
S
ED
OPEN
CLO
S
ED
OPEN
GA
S
KET
OPEN VALVE IN QUICK TE
S
T
S
UB-MODE BEFORE DI
S
A
SS
EMBLING
EF05BD271
NV
3
2.5mm
EF05BD
33
1
NV
3
6mm
50Nm (
3
6 ft-lb)+
3
0°
27mm / 1
1
/
16
''
27mm / 1
1
/
16
''
ADAPTER
NOTES:
1. Push down on valve piston to close valve before assembling.
2. After valve is assembled close valve in Quick Test sub-mode or cycle power before opening service valve.
a30-4072
DISASSEMBLY
ASSEMBLY
CAUTION
Always use a compatible lubricant to prevent the gasket
from pinching or tearing during installation. Failure to fol-
low this instruction could result in joint leakage.
CAUTION
Make sure the gasket does not become rolled or pinched while
installing the housings. Failure to follow this instruction could
cause damage to the gasket, resulting in joint leakage.
Summary of Contents for AquaForce 30XV140
Page 79: ...79 Fig 76 VFD Communication Wiring Compressor A B Fan VFD A1 A2 B1 B2...
Page 228: ...228 Fig 90 30XV Typical Field Wiring Schematic cont...
Page 229: ...229 Fig 91 30XV Standard Tier 140 275 All Voltages Power Schematic NOTE See Legend on page 226...
Page 230: ...230 Fig 92 30XV Standard Tier 300 325 All Voltages Power Schematic NOTE See Legend on page 226...
Page 240: ...240 Fig 99 30XV Communication Wiring...
Page 241: ...241 Fig 100 30XV 115V Control Wiring All Tonnages All Voltages...
Page 242: ...242 Fig 101 30XV 24V Control Wiring 30XV140 325 All Voltages...
Page 243: ...243 Fig 101 30XV 24V Control Wiring 30XV140 325 All Voltages cont...
Page 244: ...244 Fig 102 30XV 24V Control Wiring 30XV350 500 All Voltages...
Page 245: ...245 Fig 102 30XV 24V Control Wiring 30XV350 500 All Voltages cont...
Page 246: ...246 Fig 103 Component Arrangement Diagram for 30XV140 325...
Page 247: ...247 Fig 103 Component Arrangement Diagram for 30XV140 325 cont...
Page 248: ...248 Fig 104 Component Arrangement Diagram for 30XV350 500...
Page 337: ...337 APPENDIX J FACTORY SUPPLIED PUMPS cont Fig L System Information...
Page 338: ...338 APPENDIX J FACTORY SUPPLIED PUMPS cont Fig M Unit and Language Settings...
Page 341: ...341 APPENDIX J FACTORY SUPPLIED PUMPS cont Fig P Data Input 2...
Page 342: ...342 APPENDIX J FACTORY SUPPLIED PUMPS cont Fig Q Data Input 3...
Page 347: ...347 APPENDIX J FACTORY SUPPLIED PUMPS cont Fig U Pump Wiring Diagram...