18
NOTE: The gasketing of the unit to the roof curb is critical for a
watertight seal. Install gasket supplied with the roof curb as shown
in Fig. 16-18. Improperly applied gasket can also result in air leaks
and poor unit performance.
ALTERNATE UNIT SUPPORT (IN LIEU OF CURB OR
SLAB MOUNT)
A non-combustible sleeper rail can be used in the unit curb sup-
port area. If sleeper rails cannot be used, support the long sides of
the unit with a minimum of 4 equally spaced 4-in. x 4-in. (102 mm
x 102 mm) pads on each side. Locate pads so that they support the
rails. Make sure to avoid the fork openings.
Fig. 14 — Unit Leveling Tolerances
Fig. 15 — Typical Access Panel and Compressor
Locations
Table 2 — Operating Weights
A-B
0.25 (6)
B-C
0.5 (12)
A-C
0.5 (12)
MAXIMUM ALLOWABLE
DIFFERENCE IN. (MM)
A
B
C
CONTROL BOX
ACCESS PANEL
FILTER AND
INDOOR COIL
ACCESS PANEL
INDOOR BLOWER
ACCESS PANEL
GAS HEAT
ACCESS PANEL
COMPRESSOR
(EACH SIDE)
HOOD CARTON LOCATION
(REAR ACCESS PANEL)
48TC
UNITS — lb (kg)
17
20
24
28
30
Base Unit
Novation
®
Coil
1824 (829)
1839 (836)
1989 (904)
2118 (963)
N/A
RTPF Coil
1907 (867)
1922 (874)
2072 (942)
2197 (999)
2640 (1200)
Economizer
246 (112)
246 (112)
246 (112)
246 (112)
246 (112)
Powered Outlet
35 (16)
35 (16)
35 (16)
35 (16)
35 (16)
Humidi-MiZer
®
System
110 (50)
110 (50)
120 (54)
120 (54)
N/A
Curb
14-in. (356 mm)
240 (109)
240 (109)
255 (116)
255 (116)
255 (116)
24-in. (610 mm)
340 (154)
340 (154)
355 (161)
355 (161)
355 (161)
Summary of Contents for 48TC D/E17 Series
Page 5: ...5 Fig 2 48TC 17 20 Vertical Airflow...
Page 6: ...6 Fig 3 48TC 17 20 Back View and Condensate Drain Location...
Page 7: ...7 Fig 4 48TC 17 20 Corner Weights and Clearances...
Page 8: ...8 Fig 5 48TC 17 20 Bottom View...
Page 9: ...9 Fig 6 48TC 24 28 Vertical Airflow...
Page 10: ...10 Fig 7 48TC 24 28 Back View and Condensate Drain Location...
Page 11: ...11 Fig 8 48TC 24 28 Corner Weights and Clearances...
Page 12: ...12 Fig 9 48TC 24 28 Bottom View...
Page 13: ...13 Fig 10 48TC 30 Vertical Airflow...
Page 14: ...14 Fig 11 48TC 30 Back View and Condensate Drain Location...
Page 15: ...15 Fig 12 48TC 30 Corner Weights and Clearances...
Page 16: ...16 Fig 13 48TC 30 Bottom View...
Page 19: ...19 Fig 16 Roof Curb Details 17 and 20 Size Units...
Page 20: ...20 Fig 17 Roof Curb Details 24 and 28 Size Units...
Page 21: ...21 Fig 18 Roof Curb Details 30 Size Units...
Page 47: ...47 Fig 52 PremierLink Wiring Diagram...
Page 48: ...48 Fig 53 PremierLink Wiring Diagram with Humidi MiZer System...
Page 49: ...49 Fig 54 Typical RTU Open System Control Wiring Diagram...
Page 50: ...50 Fig 55 Typical RTU Open System Control Wiring Diagram with Humidi MiZer System...
Page 51: ...51 Fig 56 48TC 17 30 Control Wiring Diagram...
Page 52: ...52 Fig 57 48TC 17 30 Power Wiring Diagram 208 230 3 60...
Page 53: ...53 Fig 58 48TC 17 30 Power Wiring Diagram 460 3 60...
Page 54: ...54 Fig 59 48TC 17 30 Power Wiring Diagram 575 3 60...
Page 55: ...55 Fig 60 48TC 17 30 Control Wiring Diagram with Humidi MiZer System...
Page 56: ...56 Fig 61 48TC 17 30 Power Wiring Diagram with Humidi MiZer System 208 230 3 60...
Page 57: ...57 Fig 62 48TC 17 30 Power Wiring Diagram with Humidi MiZer System 460 3 60...
Page 58: ...58 Fig 63 48TC 17 30 Power Wiring Diagram with Humidi MiZer System 575 3 60...