NOTE

:  

 

If the transfer pump pressure is adjusted too high, it will over pressure the proportioning 
unit, and affect the ratio. 

 

H.   Apply enough pressure to the main pump to achieve a proper fan pattern. Apply material 

in accordance with the procedures recommended herein. 

 
 

A minimum of two ratio checks per shift is required.  An additional ratio check is required 
before starting a pump which has been repaired, or after a continuous down time of 
more than one hour.  Static mixers shall be examined and changed after every 2 hours 
of continuous spraying, and the mixing block and valves leading to it shall be inspected 
and cleaned after the days work is completed.  All other maintenance procedures 
specified by the pump supplier shall be followed. 

3.2 

SINGLE COMPONENT EQUIPMENT FOR THERMO-LAG 3000 SA 

 

Airless Spray Pump:      Fluid to Air Ratio of 45:1 or greater.         
 

Hopper Feed required  with a minimum ¾” outlet on high pressure 
side with an output of 3.3 gallons/minute (minimum) 

 
Gun: 

Binks lM Mastic Gun with Graco Tip Adapter 

 
Tip Size: 

0.035" - 0.045" Graco Heavy duty RAC non- diffuser tips) 

 
Fan Size: 

6" - 10" 

 
Material Hose: 

Solvent Resistant: 

                                      3/4" I.D. 50’ Max 
                                      1/2" I.D. Whip hose 25’ Max 
 

                        Pressure at Gun: 

  2500 - 3000 psi 

 

                          Air Requirements: 

  40 -100 cfm @ 100 psi per unit. Use moisture and oil traps. 

 
Static Mixer 

Standard 12 turn ¾” mixer 

 

Refer to CARBOLINE‘s application instructions for complete requirements, which can be 
found in this manual. 

Note

:  THERMO-LAG 3000-SP must be thinned up to 3% with Toluene or Plasite Thinner 

#19 only. Thinning the material will increase the pot life of the material, however it will slow 
the curing process.  CARBOLINE must approve the use of other thinners prior to start up. 

3.2.1 

EQUIPMENT STARTUP PROCEDURE 

Material shall be pre-heated to a minimum of 70

˚

(21

˚C) 

It is important that the pump and all lines are clean and free from any contamination. 

If half filled containers have been supplied, add thinner into part B and mix thoroughly.  
Stage Part B onto Part A and mix thoroughly. Thinning will decrease the amount of material 
which can be applied in one coat and decrease the rate of cure. 

If full containers are supplied, it is required to mix Parts A and B before splitting containers in 
half.  Make sure that there are equal volumes of each.  Follow instructions listed above.   

Summary of Contents for Thermo-Lag 3000

Page 1: ...THERMO LAG 3000 Fire Barrier System Application Manual Commercial Light Industrial Market ASTM E119 UL 263 NFPA 251 January 2016 Rev 4...

Page 2: ...S ACCURATE AND COMPLETE TO THE BEST OF OUR KNOWLEDGE AS OF THE DATE PRINTED THE INFORMATION IN THIS DOCUMENT IS SUBJECT TO CHANGE WITHOUT NOTICE CARBOLINE MAKES NO WARRANTY EXPRESSED OR IMPLIED OF ANY...

Page 3: ...TROL MANUAL 1 1 2 1 QUALIFICATIONS OF APPLICATORS RESPONSIBILITIES OF PERSONNEL 1 1 2 2 REQUIREMENTS 1 1 3 SAFETY PRECAUTIONS 1 1 4 DELIVERY 1 1 5 STORAGE 1 1 6 PROTECTION OF ADJACENT SURFACES 2 2 0 M...

Page 4: ...ION PROCEDURES 8 5 1 INSTALLATION OF MESH ON STRUCTURAL STEEL I AND H SECTIONS 9 5 2 FINAL THERMO LAG 3000 APPLICATION 10 5 2 1 TERMINATION ONTO NON FIREPROOFED STEEL 10 5 3 FINAL THICKNESS 10 5 4 SAM...

Page 5: ...h Details for ASTM E119 Certification UL Design No N608 Restrained and Unrestrained Beam Ratings ANSI UL263 Intertek Design No CC CA 180 02 Column ASTM E119 09c Intertek Design No CC BA 180 01 Restrai...

Page 6: ...subsections have a numerical designation For example 2 3 1 represents Chapter 2 Section 3 Subsection 1 Illustrations and drawings generally appear at the end of this document Breakdown of Information...

Page 7: ...lation Procedures in This Guide The installation steps and procedures in this guide were prepared with the best available data All of the steps and procedures presented in this guide are based upon te...

Page 8: ...and recognize their statutory obligations with regard to health and Safety 1 3 SAFETY PRECAUTIONS The Applicator shall follow standard industrial hygiene practices for the handling of chemical coating...

Page 9: ...er List All steel surfaces shall be blasted to a 1 5 2 0 mils 37 50 microns angular profile to a minimum of a SSPC SP6 Sa2 For galvanized steel surfaces see Section 4 3 Galvanized Surface Preparation...

Page 10: ...713 923 2771 Commack NY 11725 MODEL NO 631 462 2952 397 884 SQ GRACO H D Fixed Ratio Tank Mounted Pump We recommend the use of tank mounted pumps It is essential that all the equipment used by the App...

Page 11: ...from the stated pressures herein F The use of other plural component equipment with holding tanks shall be approved by CARBOLINE prior to use With the air still turned off to the main pump Adjust the...

Page 12: ...45 Graco Heavy duty RAC non diffuser tips Fan Size 6 10 Material Hose Solvent Resistant 3 4 I D 50 Max 1 2 I D Whip hose 25 Max Pressure at Gun 2500 3000 psi Air Requirements 40 100 cfm 100 psi per un...

Page 13: ...5 2 0 mils 37 50 microns to a minimum of a SSPC SP6 Sa 2 4 1 3 PRIMING Only primer systems acceptable by CARBOLINE shall be used under THERMO LAG 3000 The primer shall be applied in accordance with th...

Page 14: ...ns Prime with Carboguard 893 SG Primer 3 5 mils 75 125 microns DFT per SSPC PA2 4 4 STAINLESS STEEL SURFACE PREPARATION All steel surfaces shall be blasted to a SSPC SP7 Sa 1 with a minimum angular an...

Page 15: ...the weight of subsequent coats The thickness which can be applied in a single coat will depend on the temperature humidity applicator technique etc The time between coats is largely dependent upon am...

Page 16: ...er can be used to improve the surface quality Please read the THERMO LAG 3000 product data sheet before application commences Excessive build up of THERMO LAG 3000 in angle areas can be removed or lev...

Page 17: ...ne point shall not be less than 80 of the specified thickness The overall average thickness must be equal to or greater than the specified thickness The number of thickness checks and other issues reg...

Page 18: ...strate with a disc saw around the area to be removed Make sure that the steel substrate is not damaged A power chisel can then be used to chip away the THERMO LAG 3000 from the substrate It is essenti...

Page 19: ...ods The THERMO LAG 3000 finish appearance must be approved by the owner The specified mesh type shall be installed and butted up to the existing mesh no overlap required The final specified thickness...

Page 20: ...nt of fireproofing on ONE SIDE ONLY It is better to chip a minimal amount of fireproofing than to make all the connections unnecessarily large Follow all site specific safety standards 8 5 2 CONSIDER...

Page 21: ...Page 14 of 35 APPENDIX A THERMO LAG 3000 ACCEPTABLE PRIMER LIST...

Page 22: ...TIC 242 CARBOZINC 858 CARBOZINC 859 RUSTBOND Interior only and 2 0 mils max CARBOZINC RUSTBOND THE PRIMER SYSTEM THICKNESS RANGE SHALL BE BETWEEN 3 5 MILS 75 125 MICRONS DFT PER SSPC PA 2 ANY OTHER DR...

Page 23: ...Page 16 of 35 APPENDIX B THERMO LAG 3000 ACCEPTABLE TOPCOAT LIST...

Page 24: ...COATS CARBOGUARD 1340 CARBOTHANE 133 HB CARBOMASTIC 94 FOR INTERIOR APPLICATIONS NO TOPCOAT IS REQUIRED CONTACT CARBOLINE TESCHNICAL SERVICE FOR SPECIFIC TOPCOAT REQUIREMENTS SEE FIREPROOFING PRODUCT...

Page 25: ...Page 18 of 35 APPENDIX C THERMO LAG 3000 ASTM E119 DESIGNS...

Page 26: ...tigated by UL for compliance with applicable requirements The published information cannot always address every construction nuance encountered in the field When field issues arise it is recommended t...

Page 27: ...tor Optional Studs 3 4 in diam headed type or equivalent per AISC specifications Welded to the top flange of beam through the steel floor units 4 Welded Wire Fabric Optional 6 x 6 10 10 SWG 5 Steel Fl...

Page 28: ...intumescent coating at 0 002 in thickness and Type Carbothane 133HB topcoat or Carbothane 133MC top coat applied over intermediate coat at 0 003 in thickness 8A Top Coat As an alternate to Item 4 Type...

Page 29: ...Page 22 of 35 DESIGN NO CC CA 180 02 Formerly NUC CA 180 02 OPL DESIGN NO C 301 CERTIFIED PRODUCT Fire Resistive Coating MODEL Thermo Lag 3000 COLUMN RATING 3 HOUR OR LESS...

Page 30: ...ofing Item 2A greater than 0 24 6mm install fiberglass mesh at 0 12 3mm from solid structural steel column Item 1 Overlap fiberglass mesh a minimum 1 2 13mm at seams i Method for solid structural stee...

Page 31: ...0 50 210 0 64 0 17 0 25 0 33 0 42 0 51 220 0 61 0 17 0 26 0 34 0 43 0 53 230 0 58 0 18 0 26 0 35 0 44 0 54 240 0 56 0 18 0 27 0 36 0 45 0 55 250 0 53 0 19 0 28 0 37 0 46 0 56 260 0 51 0 19 0 28 0 37 0...

Page 32: ...DESIGN NO CC BA 180 01 Formerly NUC BA 180 01 OPL DESIGN NO B 303 CERTIFIED PRODUCT Fire Resistive Coating MODEL Thermo Lag 3000 CERTIFIED PRODUCT Insulation RESTRAINED OR UNRESTRAINED BEAM RATING 3...

Page 33: ...ckness of the intumescent fireproofing Item 4A of 0 24 6mm or less install mesh at middle depth of the intumescent fireproofing Item 4A For final thickness of the intumescent fireproofing Item 4A grea...

Page 34: ...0 46 180 0 74 0 15 0 23 0 30 0 39 0 47 190 0 70 0 16 0 24 0 31 0 40 0 48 200 0 67 0 16 0 24 0 32 0 41 0 50 210 0 64 0 17 0 25 0 33 0 42 0 51 220 0 61 0 17 0 26 0 34 0 43 0 53 230 0 58 0 18 0 26 0 35 0...

Page 35: ...age 28 of 35 DESIGN NO CC CA 180 03 Formerly NUC CA 180 03 OPL DESIGN NO C 304 NPD CERTIFIED PRODUCT Fire Resistive Coating MODEL Thermo Lag 3000 COLUMN IMO NPD HYDROCARBON CURVE RATING 3 HOUR OR LESS...

Page 36: ...Item 2B CERTIFIED PRODUCT Fire Resistive Coating MODEL Thermo Lag 3000 B High Temperature Fabric For final thickness of the intumescent fireproofing Item 2A of 6mm 0 24 or less install high temperatu...

Page 37: ...1 0 13 0 19 0 33 0 47 0 61 130 1 03 0 13 0 20 0 35 0 49 0 63 140 0 95 0 13 0 21 0 36 0 51 0 66 150 0 89 0 13 0 22 0 37 0 53 0 69 160 0 84 0 13 0 22 0 39 0 55 0 71 170 0 79 0 13 0 23 0 40 0 57 0 73 180...

Page 38: ...Page 31 of 35 APPENDIX D THERMO LAG 3000 TYPICAL APPLICATION LOGS...

Page 39: ...Page 32 of 35 If performed by other than THERMO LAG 3000 Applicator not inspection and acceptance date by Applicator QC Inspector Supervisor...

Page 40: ...Page 33 of 35...

Page 41: ...Page 34 of 35...

Page 42: ...Page 35 of 35...

Reviews: