PM 1001606 000 07
Device handbook CENTRAX CU3000-CU5000
32/106
6. Commissioning
Before commissioning you have to check if the connection data of the device match the data
of the plant (see nameplates).
If so, you can start to put the device into operation by switching on the power supply and the
measurement inputs.
Measurement input
Input voltage
Input current
System frequency
1 Works no.
2 Test and conformity marks
3 Assignment voltage inputs
4 Assignment current inputs
5 Assignment power supply
6 Load capacity relay
outputs
…………………………………………………………………………………………………………………………
Measurement input
Input voltage
Input current
System frequency
1 Works no.
2 Test and conformity marks
3 Assignment voltage inputs
4 Assignment current inputs
5 Assignment power supply
6 Load capacity relay
outputs