10-27
phn-4750_003v006
Chapter 10
Acceptance and Commissioning
Procedures
This chapter provides Cambium's recommended Acceptance and Commissioning Procedure for PTP
820. Acceptance and commissioning should be performed after initial setup is complete.
The purpose of this procedure is to verify correct installation and operation of the installed link and
the interoperability with customer end equipment.
Cambium's Acceptance and Commissioning procedure includes the following stages:
•
Site Acceptance Procedure
•
Commissioning of radio link
The Site Acceptance Procedure is a checklist that summarizes the installation requirements of the
site at which the products were installed.
The commissioning tests cover the required configuration information that should be recorded, and
the tests that should be performed on the radio link.
Site Acceptance Procedure
The purpose of the following procedures is to verify that all installation requirements were noted
and checked. Following this procedure will ensure proper, long-lasting, and safe operation of the
product.
The checklist below summarizes the installation requirements of the site.
SITE ACCEPTANCE CHECKLIST
1. SITE INFORMATION
Customer:
Radio model:
Site name:
Site code:
Radio link code:
Site address:
2. ANTENNA MOUNTING
Antenna mount type:
Mount is of sufficient height to clear local obstructions
OK
Mount is safely positioned to not cause a safety hazard
OK
Mount is secure and perpendicular
OK