CalAmp | TTU-7xx Install Guide
MBUD-0239v2
Page 15
Figure 9: Lanyard connected
15.
Remove the activation magnet from the front of the device enclosure in order to activate device
reporting.
8 INTERMODAL CONTAINER DOOR SCREW MOUNT INSTALLATION
The following steps outline the procedure for Intermodal Container Door Screw Mount Installation. Prior
to beginning the installation, verify that you have the proper tools and materials.
Tools and Materials:
Cordless Drill
3/16” Drill Bit
3/8” Open-End Wrench
Cross Tip Drill Attachment (or 1/8” Hex Allen Wrench)
Scratch Awl
RTV Sealant
To Install Intermodal Container Door Screw Mount:
1.
Tag equipment with appropriate signage to indicate Lockout/Tagout procedure is in process.
Installers should be properly trained in LOTO procedures in accordance with OSHA regulations.