5 | Installation
8 / 28
0870203784_WZ2400A_-0001_IM_en
• Make sure that enough space remains for maintenance work.
• Make sure that the machine is placed or mounted horizontally, a maximum of 1° in
any direction is acceptable.
• Make sure that the machine is secured either from the four feet or from the discharge
flange.
• Check the oil level, see
• Make sure that all provided covers, guards, hoods, etc. are mounted.
• Make sure that the cooling water complies with the requirements, see
5.2 Connecting Lines / Pipes
• Remove all protective covers before installation.
• Make sure that the connection lines cause no stress on the machine‘s connection; if
necessary use flexible joints.
• Make sure that the line size of the connection lines over the entire length is at least as
large as the connections of the machine.
In case of long connection lines it is advisable to use larger line sizes in order to avoid a
loss of efficiency. Seek advice from your Busch representative.
5.2.1 Gas Flow Variants
The machine can be installed in different ways:
Lateral discharge (Optional)
Vertical gas flow